
|

|

December 4, 2000
To:
File
From: Christopher
R. Bean, P.E.
Date: December 6,
2000
RE:
VTrans Pittsford-Brandon NH
019-3(49)SC CLD Reference No.
00-0219,00-0248,00-0215 and 00-0216
Subject: US
Route 7 Upgrade Steering Committee Meeting 12/04/00
Location:
Pittsford Municipal Building
| Attendees: |
|
|
|
|
* |
Peg Flory |
Town of
Pittsford |
|
* |
James O'Gorman |
Town of
Pittsford |
|
* |
Hank Pelkey |
Town of
Pittsford |
|
* |
Lynn Saunders |
Town of
Brandon |
|
* |
Dan Peterson |
VTrans, Project
Manager |
|
* |
Greg Riley |
VTrans, Planning
Coordinator |
|
* |
Duncan Wilkie |
VTrans,
Archaeologist |
|
|
Scott Newman |
VTrans, Historic
Resources |
|
* |
Chris Borstel |
Louis Berger &
Associates |
|
|
Roy M. Newton |
Brandon-Pittsford
Reporter |
|
|
Ed Barna |
Rutland
Herald |
|
|
Mark
Germanowski |
Rutland Regional Planning
Commission |
|
|
Bob Wood |
Representative, District
R-2 |
|
|
Jason Stone |
CLD |
|
|
Kurt Beek |
CLD |
|
|
Wayne Husband |
CLD |
|
* |
Chris Bean |
CLD |
|
* |
Steering
Committee Member |
Notes From Meeting
- Conceptual Plans
Development
- Review Progress Prints/Status of
Field Survey
Wayne Husband updated the
Committee on the status of the Conceptual Plans. Wayne presented a
draft set of plans for Project Segment 4 as an example for discussion.
Wayne stated that the level of design detail that goes into Conceptual
Plans is much more advanced than the planning level detail that goes
into a Scoping Report. The purpose of Conceptual Plans is to establish
line and grade of the highway, the roadway box and the limits of work
(slope lines). The plans include a title sheet, plan sheets (a bird's
eye view), profile sheets, cross sections, and eventually all of the
detail sheets. Wayne added that the field survey and plan annotation
are complete, though Vermont Survey and Engineering remains under
contract in the event that additional survey is required. Dan Peterson
asked whether the plans would show right-of-way (ROW) information. It
was later confirmed that existing ROW information will be shown on the
plans. Chris Bean added that the Conceptual Plans for the six project
segments are targeted for completion by January, 2001
- Mailbox Locations in Pittsford
Village Chris Bean began this
discussion, noting that ideally this issue might have been identified
in the Scoping Report, as it could impact the design significantly. He
then explained the space constraints involved with fitting the
proposed pavement typical in the Pittsford Village area, and
maintaining mailboxes in front of residences along both sides of US 7,
as they are located today. Ideally, mailboxes would be located between
the proposed curb and the sidewalk, in a panel ranging between 2 and
3.5 feet wide. To avoid encroaching on the travel lanes, an 8-foot
shoulder would be needed to allow the delivery vehicles adequate room
outside the traveled way. In many areas the available width will not
accommodate such a treatment. The currently proposed roadway shoulder
width (4 feet) does not allow enough width for delivery vehicles.
Chris noted that a reduced typical (shoulder width) has been used in
other locations, but the traffic volumes in those areas do not
approach the magnitude of traffic on US 7, and a reduced shoulder
width is not be recommended in this project area. Various options were
then discussed, such as locating all mailboxes on one side of the
roadway, placing "cluster" boxes with turnouts at fewer locations, and
implementing door-to-door delivery. The pros and cons of each were
discussed, and the consensus of the Committee was to pursue
implementing door-to-door delivery. In preliminary discussions between
James O'Gorman and the Postmaster, the Postmaster did not support
door-to-door delivery as an option. A majority of the Committee felt
that issues surrounding the delivery of mail should not dictate the
width of the future highway. Peg Flory indicated that she would
contact the Postmaster, as well as the newspapers, to discuss the
matter further and determine what criteria must be met before
door-to-door delivery will be considered. Scott Newman added that
the argument for door to door delivery versus greater levels of
encroachment onto historic properties necessary to accommodate wider
pavement widths could be supported from a Section 106 standpoint as
well.
- Act 250
Coordination
Chris Bean summarized the discussions
from the Act 250 Coordination Meeting held on October 25, 2000. A Master
Plan approach will be taken for the overall US 7 Project. The
application will be made when Preliminary Plans are complete. The
Environmental Board will issue Final Affirmative Findings (FAFs) for
issues that are adequately addressed, and then will revisit issues
associated with each project segment on an as-needed basis, as
information becomes available. FAFs are in effect for five years, and
can be extended as necessary. A pre-application meeting with the DEC,
VTrans, and CLD will also be held to re-famililarize the involved
parties with the project and the agreed upon permit strategy.
- Vermont Division of Historic
Preservation Coordination (DHP)
Scott Newman informed the Committee of
the DHP's position regarding the Whitaker Building, located at the "bank
corner" in downtown Brandon. It is the DHP's position that a
satisfactory argument for impacting the building cannot be made, and
that the building must remain in place.
The Bloodworth property and house were
also discussed. This property would be impacted by the project unless
extraordinary measures, such as tall retaining walls, were implemented.
Scott Newman has indicated that the historic integrity of the property
has diminished to the point where such measures are not warranted, and
that the house may be either set back on the property, marketed for
relocation elsewhere, or, if that effort is unsuccessful, the house
could be demolished. Scott asked for guidance as to when these decisions
need to be made, so that the necessary mitigation and coordination will
not delay the project schedule. Early acquisition of the property is
also being considered. It was decided to wait until the Conceptual Plans
are complete to set a timeline for these decisions.
- Update on Bypass
Studies
Jason Stone asked whether either of the
Bypass Steering Committees had designated additional representatives. As
it now stands, Pittsford still needs one representative, and Brandon
needs two representatives. The Committees will work on nominating the
new members.
Jason explained that CLD is developing a
Draft Purpose and Need Statement. This will be forwarded to the Bypass
Steering Committees a week or two in advance of the Public Informational
Meeting (PIM), which is scheduled for 7:00 PM on Thursday, January 11,
2001, at the Otter Valley Union High School, for their review and
comment. (This PIM was confirmed subsequent to this Steering Committee
Meeting.)
CLD is also working to develop a press
release for the PIM. Advance notice of the PIM will go to the area
newspapers as usual, but an informational insert will also be created to
be delivered with newspapers several days in advance of the meeting. A
draft press release and insert will also be forwarded to the Committees
for their review and comment.
Constraints mapping is progressing. A
related initiative in association with the Orton Foundation was also
discussed; Community Viz is a computer software that models development
and other changes in land use. The Town of Brandon is participating in a
demonstration of the software, which allows a bird's eye view of land
use changes as they occur over time. It is possible that the software
could be used to evaluate the effects of a Bypass as it relates to land
use. (CLD recently attended a demonstration of this software. A memo
summarizing that meeting will be distributed.
- Archeological Survey
Update
Duncan Wilkie indicated that
archeological issues for at least four, and probably five, of the six
project segments have been cleared. The area around the Fort Vengeance
Monument will require further investigation. It is likely that a
National Register eligible site exists there, either in association with
the fort itself, or the subsequent use of some of the fort buildings.
Chris Borstel presented a cross section of the archeological deposits in
this area to show their relationship to the existing road and the
proposed improvements. Various scenarios of avoidance, mitigation, and
early property acquisition were discussed. Duncan asked VTrans what
information is needed to proceed.
The Steering Committee asked Louis
Berger Associates and CLD to work together to develop a matrix of the
various alternatives to be considered in order to resolve the
outstanding archeological issues. The Committee does not want the design of the
highway to be compromised to avoid archeological resources whose
significance has not been positively determined. The attendees are very
concerned about highway safety in this particular
area.
- Other Issues
Roy Newton asked that a reminder of
upcoming meetings be sent to the Committee and other attendees two weeks
in advance of scheduled meetings. Chris Bean agreed to do so. Chris also
informed the Committee that notes of the Bypass and Upgrade Steering
Committee Meetings are available on CLD's web site
Chris Bean explained that some
consideration for concrete versus bituminous pavement is necessary. He
suggested that there are pros and cons with either treatment. The
Committee expressed support for the bituminous pavement option as
opposed to the new concrete.
Lynn Saunders mentioned there was a
Public Hearing scheduled for Tuesday, December 5th, to present the
Rutland Regional Transportation Plan. The outcome of the meeting could
have some bearing on future roadway construction in their region. She
encouraged others to attend.
- Next Meetings
- US 7 Upgrade Steering
Committee
Monday, February 5, 2001, from 4:00 to 7:00 PM, at the
Brandon Fire Station.
- Initial US 7 Bypass Public
Informational Meeting
Thursday, January 11, 2001, from 7:00
to 9:00 PM, at the Otter Valley Union High School
Auditorium.
- Brandon Bypass Steering Committee
Meeting
Monday, January 29, 2001, from 4:00 to 5:30 PM, at the
Brandon Fire Station.
- Pittsford Bypass Steering Committee
Meeting
Monday, January 29, 2001, from 6:00 to 7:30 PM, at
the Pittsford Municipal Building.
CRB: cww
| cc: |
Lynn Saunders |
Dennis
Benjamin |
|
Peg Flory |
John
Narowski |
|
Hank Pelkey |
Mark
Germanowski |
|
Richard Baker |
Susie
Leonard |
|
James
O'Gorman |
Chris
Borstel |
|
Mike Balch |
Kathleen
Ryan |
|
Dan Peterson |
Gary A.
Klinefelter |
|
Alan Neveau |
Roy Newton |
|
Scott Newman |
Ed Barna |
|
Duncan Wilkie |
Frank
Farnsworth |
|
Greg Riley |
|
|
|
|
|
|
|
|