US Route 7 Upgrade Steering
Committee
October 16, 2000
To: File
From: Christopher R. Bean,
P.E.
Date: October 24, 2000
RE:
VTrans
Pittsford-Brandon NH
019-3(49)SC
CLD Reference No.
00-0219,00-0248,00-0215 and 00-0216
Subject: US Route 7 Upgrade
Steering Committee Meeting 10/16/00
Location: Brandon Fire Station
| Attendees: |
|
|
|
|
* |
Peg Flory |
Town of Pittsford |
|
* |
James O'Gorman |
Town of Pittsford |
|
* |
Harry McKinlay |
Town of Pittsford |
|
* |
Michael Balch |
Town of Brandon |
|
* |
Lynn Saunders |
Town of Brandon |
|
* |
Richard Baker |
Town of Brandon |
|
|
Al Stevens |
Brandon Resident |
|
|
Jim McKinnell |
Brandon Resident |
|
|
Pat Read |
Brandon Resident |
|
|
Jessica Doos |
Sudbury Resident |
|
* |
Dan Peterson |
VTrans, Project Manager |
|
* |
Greg Riley |
VTrans, Planning Coordinator |
|
* |
Duncan Wilkie |
VTrans, Archaeologist |
|
|
Scott Newman |
VTrans, Historic Resources |
|
* |
Chris Borstel |
Louis Berger & Associates |
|
|
Roy M. Newton |
Brandon-Pittsford Reporter |
|
|
Ed Barna |
Rutland Herald |
|
|
Frank Farnsworth |
Otter Valley Press |
|
|
Jason Stone |
CLD |
|
|
Kurt Beek |
CLD |
|
|
Wayne Husband |
CLD |
|
* |
Chris Bean |
CLD |
|
* |
Steering Committee
Member |
1. Archeological Study Update
Duncan Wilkie introduced Chris Borstel who explained the status of the
archaeological study. Chris used the overhead projector to summarize in
detail the study conclusions to date. Copies of the overhead slides are
attached to the file copy of this memo. In summary, the archeological
studies have determined the following:
- Phase 1 studies are 90% complete. Phase 2 studies are 33% complete.
- Five archeological sites have been identified. Three are considered
to be prehistoric (pre-European settlement) and two are historic.
- Four out of the five sites will require additional work to determine
their Historic National Register eligibility. One prehistoric site will
be recommended to be ruled out without additional study. The other
prehistoric sites will not likely be determined eligible. The two
historic sites are still under study and the determination as to their
eligibility cannot be made at this time.
- Field studies at the Fort Vengeance Monument site have not
identified any fort features; however, some domestic building foundation
remnants have been uncovered. It is Chris's opinion at this time that
there are three sites where the fort may have existed. Chris is in the
process of performing additional studies and research to make a final
determination.
-
The monument includes an inscription noting that the remains of Caleb
Houghton's body were removed to this location. To date no validation of
this move has been discovered. In fact, the determination has been made
that the monument has actually been moved from its original location, so
there is additional investigation needed before a determination can be
made as to whether the remains are present in the vicinity of the
monument.
-
A summary of all the archaeological studies will be completed prior
to the next Steering Committee Meeting (12/4/00). This determination
will identify any remaining sensitive issues that need to be dealt with
along the entire project length.
2. Conceptual Plans Development
- Field Survey
Vermont Survey and Engineering (VSE) has
nearly completed their field work, and they are in the process of
completing the annotation (labeling of trees, houses, driveways, etc.)
of the base survey. CLD expects to receive this information in about a
month. The updated detail will be shown on the Conceptual Pans. VSE is
also under contract to assist CLD with future spot location survey
requests as necessary for the duration of the project as changes occur
along the corridor.
-
Whitaker Building in Downtown Brandon
The engineering
studies confirm the Scoping Report's recommendations that the access
driveway across from Vermont 73, which currently serves as the exit from
the drive-in bank and real estate office, cannot continue to be open as
part of the project. Access to the building would be from its single,
one-lane width, entrance located on the west side of the building. Wayne
then explained that another option, which would relocate the alignment
further to the west to flatten the horizontal curve, was considered.
This option would have required the taking of the building; however, it
would have also resulted in an additional park area and a smoother,
safer roadway alignment. Scott Newman indicated that he would review the
alternative of taking the building, which resulted in the enhancement of
the park area, with DHP again to determine whether that option could be
reconsidered. The Committee expressed support for this particular
realignment alternative, and they also questioned the historic
significance of the building. They specifically mentioned the modern
building renovations.
-
Typical Section - Pavement Design
The proposed pavement
design has been presented to the VTrans Pavement Design Committee, and
agreement has been reached on the typical throughout all six projects.
The decision has been made to remove the concrete in its entirety and
reconstruct the roadway with new pavement and base section throughout.
This will allow for optimization of the vertical alignment design, since
the existing concrete pavement will no longer control the depth of
excavation in certain areas. The issue of what will be done with the
concrete pavement was raised. An option of utilizing it, perhaps as part
of the proposed base section, was discussed. This item will be continued
on next month's agenda to update the Committee on further decisions. The
Towns asked if we should begin the coordination of utilities now, since
there are improvements planned with the Village of Pittsford. Harry
McKinlay mentioned that Green Mountain Engineering was putting out a
contract to reconstruct the sewer in Pittsford. CLD subsequently called
Green Mountain Engineering, and we have since received their contract
documents for the sewer work. The scope of this sewer project involves
mostly realigning of existing sewer lines.
-
Access Management
The Project Definition Team had requested
that an access management policy be written for the project to ensure
uniform application of driveway entrance design. CLD has reviewed the
VTrans Draft Driveway Design Manual and concluded that from a design
standpoint, publishing a new policy specifically for this project does
not appear to be appropriate. Instead, CLD reviewed the current standard
treatments of driveways and openings with the Committee (standard detail
sheet B-71). CLD will continue using this as the guideline and apply it
in the Conceptual Plans development. No further development of an access
management policy for this project is planned.
3. Vermont Division of Historic Preservation
Coordination
Scott Newman requested that he field review the proposed layouts with
CLD prior to the Conceptual Plans Submission. At that time, he may suggest
mitigation measures at certain locations, which will be documented in the
Environmental Permit Applications.
Scott updated the Committee on the status of the Bloodworth residence,
which is located in Pittsford, south of Route 3 at the southerly end of
the southbound truck lane on the west side of Route 7.
Scott indicated that the owners feel that the house is historic;
therefore, if the project requires that it be taken, the permitting
process will involve advertising the house for relocation. If that proves
unsuccessful, then demolition of the house would be possible.
Scott indicated that his responsibility includes documenting the
historic inventory and including that documentation as part of the
environmental permit documentation. This information will be used to
determine the historic eligibility of buildings.
Scott reemphasized his understanding that environmental documentation,
including the CE, Section 106, and Section 4(f), can be developed
independently for each of the six projects. This is consistent with our
previous understanding. This is important, since it will allow for an
individual project to proceed without delay if historic related issues do
not require extended coordination.
4. Landscape Plans
At the previous August 28, 2000 Steering Committee Meeting, the
committee asked CLD to coordinate the design of the roadway project with
the landscape design for downtown Brandon that is currently being worked
on by Landworks. CLD has contacted Landworks and received a copy of their
conceptual plans. A copy of the plans was reviewed with the committee. The
Steering Committee acknowledged that the final design of the landscaping
plans along Route 7 would need to wait until the highway design plans were
further advanced.
5. Act 250 Coordination
A meeting has been set up with the Act 250 District Commissioner on
Wednesday, October 25, at the District Commission office in Rutland.
Attendees are expected to include Dan Peterson, Assistant Attorney General
Scott Whitted, Scott Newman from VTrans, Lynn Saunders from Brandon and a
representative from Pittsford, and Bill Grace and Chris Bean from CLD. The
purpose of this meeting will be to discuss the requirements associated
with the Act 250 permitting for this project. The goal will be to submit
all six projects in a conceptual form, which will allow for individual
projects to be approved as the design processes are completed. This way,
should an individual project be delayed for one reason or another, it will
not hold up the permit approval of the other projects.
6. Project Schedule to Construction
A full discussion of three schedules took place. Copies of the
schedules were distributed at the meeting and are attached to the original
copy of this memo. All the schedules were aggressive, based on recent
VTrans project schedule history. They included a VTrans traditional
project schedule which would take about four-and-a-half years to
advertise, a modified VTrans traditional project schedule which could cut
off about six months, and a municipally-managed project which Brandon
qualifies for and could cut off about a year. Several items were
discussed, including concern voiced for the length of the right-of-way
process. The overall consensus of the Steering Committee was that all the
schedules were unacceptable, since they require too much time prior to
construction. It was agreed that the Committee, as well as the engineers,
will review the information, and the project schedule will be added to the
next meeting agenda for discussion.
7. Bypass Projects
A handout summarizing the purpose of the bypass scoping projects was
distributed. A copy is attached to the original of this memo. It was
emphasized that a separate Bypass Project Steering Committee will be
developed for each town. Each Town's Committee will include a
representative from the other Town. The bypass studies will determine
whether a more detailed environmental impact statement type of study is
warranted for the Pittsford and/or Brandon bypasses.
- Contract Status
Dan Peterson indicated that the intention
will be to obtain formal federal authorization for CLD to proceed with
this work prior to the October 25th Origin-Destination Traffic Survey.
Up until that point, CLD will charge time associated with the bypass
projects to the Conceptual Plans projects.
-
Team and Responsibilities
CLD will be completing the
majority of the work. However, in addition, the Rutland Regional
Planning Commission will complete the socioeconomic portion of the
study, which includes impacts to businesses, growth, and sprawl.
Kathleen Ryan is on the team to complete visual and aesthetics impacts
of the bypass options.
-
Project Schedule
A project schedule was handed out for
review. The initial meetings will include a Steering Committee Meeting
and a Public Meeting. The bypass studies are proposed to be completed by
the end of July 2001. This date is firm, as CLD's environmental retainer
contract will expire at that time.
-
Origin-Destination Study
Handouts describing the O-D Study
were distributed. The location of the study will be just south of
McConnell Road, and it will involve surveying both northbound and
southbound traffic during the daylight hours on October 25, 2000,
weather permitting. A question was asked as to whether it would make
sense to survey traffic that is coming from Pittsford and entering and
exiting the Otter Valley High School. In addition, a concern was voiced
about not continuing the survey through the evening hours. The Committee
felt that the truck traffic in the evening is excessive and that
bypasses would be utilized significantly during that time period. It was
agreed that the survey of the trucks at night could possibly be done
without stopping and questioning the drivers. These issues will be
discussed with the CLD Traffic Team and considered in completing the
traffic documentation.
-
Identification of Steering Committees in Each Town
It was
agreed that each Town would appoint five members, and the sixth member
would be from the other Town. In addition, Dan Peterson or the future
VTrans Manager of the bypass projects would serve on the Committees, as
well as representatives from CLD. The Town Managers will report back to
CLD as to the composition of the Committees so that CLD can send
invitations for future meetings to the appropriate people.
-
Meetings
The initial Bypass Steering Committee Meeting will
be held at 4:00 PM on Monday, November 13, 2000 at the Brandon Fire
Station. It was agreed that the initial Bypass Steering Committee
Meeting and the Public Informational Meeting will be combined for each
community. From that point forward, the Bypass Steering Committee
meetings will be held independently. The initial Bypass Public
Informational Meeting will be held on Thursday, December 14, 2000 at 7
PM at the Otter Valley High School. The high school's availability on
this date needs to be confirmed.
8. Next Conceptual Plans Steering Committee Meeting
The next Conceptual Plans Steering Committee meeting will be held on
Monday, December 4, 2000, at the Pittsford Municipal Building.
CRB:cww
Attachments
| cc: |
Lynn Saunders |
Mark Germanowski |
|
Peg Flory |
Susie Leonard |
|
Harry McKinley |
Chris Borstel |
|
Richard Baker |
Kathleen Ryan |
|
James O'Gorman |
Gary A. Klinefelter |
|
Mike Balch |
Roy Newton |
|
Dan Peterson |
Ed Barna |
|
Alan Neveau |
Frank Farnsworth |
|
Scott Newman |
Chris Bean |
|
Duncan Wilkie |
Wayne Husband |
|
Greg Riley |
Kurt Beek |
|
Dennis Benjamin |
Jason Stone |
|
John Narowski |
|