M
E M O R A N D U M
TO: File
FROM: William P. Grace
DATE: July 18, 2001
RE: Derry-Londonderry Exit
4A
Environmental
Impact Statement
CLD Reference No.
97-0209
SUBJECT: Resource Agency Meeting
LOCATION: NHDOT Highway
Design Conference Room
ATTENDEES: *Jeff Brillhart NHDOT
*Marc
Laurin NHDOT
Mark
Hemmerlein NHDOT
Charlie
Hood NHDOT
Bill
Hauser NHDOT
*Bill
O’Donnell FHWA
Harry
Kinter FHWA
Richard
Roach ACOE
Mark
Kern EPA
Lori
Sommer NHDES
Gino
Infascelli NHDES
*George
Sioras Town of Derry
**Roberta
Robie Town of Derry
Bill
Grace CLD
Jamie
Paine CLD
*TAC Members
**CATF Member
Purpose of Meeting: To discuss two new alternatives and recommendations for the
remaining alternatives to be studied through the Draft EIS phase.
Items Discussed:
1.
Review of Remaining
Alternatives
Bill Grace gave a brief
overview of the remaining alternatives.
The four new location alternatives are known as A (southern interchange – Tsienneto Road), B (southern interchange – bypass of Tsienneto Road), C (northern interchange – Route 28 –
bypass of Tsienneto Road), and D
(northern interchange – Route 28 – Tsienneto Road). The minor upgrade of NH Route 102 is Alternative F.
Two different locations for a potential new interchange are being
considered. One interchange is located
0.4 miles north of the Ash Street overpass.
Alternatives A and B would both begin at this point and extend easterly
from there. The second interchange is
located just south of the Stonehenge Road overpass. Alternatives C and D would begin there and extend to the south
and east.
At the conclusion of the
last Resource Agency meeting held on 9/20/00, the Agencies recommended that
Alternatives A, B, C, D and F, as well as the no-build alternative, be carried
forward for more detailed studies through the Draft EIS phase. The Resource Agencies felt that continuing
with only one new interchange location would not represent a reasonable range
of alternatives and that Alternatives B and C would be more difficult to accept
and to permit since those options would have slightly more negative impacts to
natural resources.
New alternatives involving
improvements to Londonderry Road and connections to the existing Alternatives A
and B were suggested by an individual at the January, 2001, Public
Informational Meetings. FHWA and NHDOT
felt those options might have some merit and suggested that the Towns
investigate these new options further.
CLD was then directed by the Towns to develop pre-conceptual plans and
initial impact studies and report back to the Technical Advisory Committee
(TAC) and the Local Administrative Oversight Committee (LAOC). A joint meeting with the TAC and LAOC was
held on July 17, 2001. It was
determined that although Alternatives G and H provided only minimal traffic
reductions along Broadway and involved substantial right-of-way impacts on
Londonderry Road, more input from the Resource Agencies, the Town Councils and
the public should be solicited before these alternatives are removed from
further consideration.
2. Possible
Alternatives ‘G’ and ‘H’
CLD developed a conceptual
plan showing a hybrid alternative (Alternative G) using Londonderry Road and
connecting to Alternative A. Bill Grace
explained that this alternative would begin on NH Route 102 (Broadway) just
east of the Exit 4 ramps and require modifications to the Broadway/Londonderry
Road intersection, providing a primary through movement for traffic along
Londonderry Road and a secondary movement for traffic continuing down Broadway. This intersection would be signalized. A second hybrid alternative (Alternative H)
also uses Londonderry Road and would connect to Alternative B. A preliminary environmental impact matrix
and a 1 inch/2000 ft. plan view including the two new alternatives and the
other remaining alternatives (A, B, C, D, and F) was distributed for
discussion.
Both Alternatives G and H
would require the expansion of Londonderry Road to five lanes and would involve
substantial right-of-way impacts to homes and businesses along Londonderry Road
and NH Route 102. These include the
Derry Plaza, which contains seven businesses.
The design of Londonderry Road was modified to avoid taking two new
commercial/industrial buildings on the easterly side of Londonderry Road and to
minimize other right-of-way acquisitions.
Alternative G would require
the acquisition of 21 buildings (10 residential and 11 commercial), impact 1.3
acres of wetlands, 11 historic properties including 6 buildings and would cost
approximately $13.4 million, including engineering design, construction, and
right-of-way.
Alternative H would require
the acquisition of 24 buildings (13 residential and 11 commercial), impact 4.2
acres of wetlands, 4 historic properties (no buildings), and would cost
approximately $15.5 million for design, construction, and right-of-way.
3. Comments and
Concerns for Alternatives G and H
Richard Roach asked about
wetland impacts. CLD explained that
there is a wetland system just east of Londonderry Road, and there would be
some minor impacts there. However, the
new alternatives have less total wetland impacts than Alternatives A and B
because there are wetland impacts associated with a new interchange for A and B
that are not involved with Alternatives G and H.
Mr. Roach noted that NEPA
and Section 404 regulations require that the natural, socio-economic and
cultural environments need to be considered and a reasonable range of
alternatives need to be carried forward through the Draft EIS. The new alternatives have serious impacts to
the socio-economic environment. The
Towns need to collectively decide if these impacts are reasonable and
acceptable.
Potential traffic benefits
along Broadway if the new alternatives progressed were discussed. Southern NH Planning Commission completed a
traffic model analysis for the new alternatives. Alternatives G and H would provide only minimal traffic volume
reductions on Broadway. The new
alternatives would provide less relief (for Broadway) than the two northerly
alternatives (C and D) and much less relief than Alternatives A and B.
Richard Roach asked how the
Towns of Derry and Londonderry felt about the impacts associated with the new
alternatives and the perceived traffic benefits. George Sioras responded that the Town of Derry feels that the new
alternatives provide little traffic relief and also would require substantial
right-of-way impacts. The Town of Derry
would not be opposed to eliminating these alternatives from further study. The primary goal of the project is to
relieve traffic congestion on Broadway.
Economic development is secondary.
George also noted that these new alternatives were mentioned at the
January, 2001, Public Informational Meetings by a Londonderry Town Councilor,
but were also discussed during the very early phases of the original Exit 4A
discussions back in the mid-1980’s.
Bill Grace noted that the Town of Londonderry has not submitted a united
official position on the new alternatives.
Upcoming meetings with each of the Town Councils will be held in the
near future to discuss this issue.
Mark Kern of the EPA noted
that the traffic reductions of the new alternatives were relatively minor. He also asked if the EIS process had begun
to consider secondary impacts beyond the Project Study Area limits. Bill Grace responded that this issue had not
yet been evaluated. George Sioras noted
that residential development in Chester and Sandown is currently occurring at a
rapidly growing pace, regardless of potential for Exit 4A improvements. George noted that approximately 400 building
lots have been approved in Chester and await construction.
4. Removing Alternatives
The Resource Agencies in
attendance were asked if it would be acceptable to remove the new alternatives
from further consideration. The group
did not feel strongly one way or the other and would not oppose removal from
further consideration. The Towns will
need public input to determine if these alternatives should be carried forward.
5.
Next Steps
a)
Town Councilor Meetings
The new alternatives will be presented to the
Derry and Londonderry Town Councilors and the official position of each town
will be solicited.
b) Public Informational Meeting
One joint public meeting,
with appropriate announcement in local newspapers and on local cable access
channels, will be held to notify the public that Alternatives G and H have been
developed and are not being proposed for further study. Public input will be solicited. Input from the general public is critical,
and the rationale behind these decisions should be well documented.
WPG:cww
cc: Technical
Advisory Committee (TAC): Project
Team:
Derry: George Sioras, Alan Swan, Doug
Rathburn Victoria Bunker
Londonderry: Andre Garron and Janusz Czyzowski Lynn Monroe (Preservation
Co.)
FHWA: Bill O’Donnell, Butch Waidelich Bruce Mayberry
NHDOT: David J. Brillhart and Marc Laurin
SNHPC: Moni Sharma
Local
Administrative Oversight Committee (LAOC):
Carol
Granfield Derry Town
Administrator
James
MacEachern Derry Town Councilor
Edmund
Boutin, Esq. Derry Counsel
Troy
Brown Londonderry
Interim Town Manager
Andrew
Greco Londonderry Town
Councilor
Robert
Carr, Esq. Londonderry Counsel
Citizens Advisory Task Force
(CATF):
Derry: Londonderry:
George Sioras Troy Brown
Albert
Doolittle Jim Anagnos
Roberta
Robie Eugene Harrington
Jack
Dowd Jennifer A.
Sollars
Barbara
Concannon Gerry Shuck
Frank
Mazzuchelli Rep. Sherman Packard
Suzanne
Regali