M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: January 11, 2001
RE: VTrans
Pittsford and Brandon
US
Route 7 Bypass Scoping Studies
CLD Reference Nos.
00-0215 and 00-0216
SUBJECT: Public Informational Meeting
LOCATION: Otter Valley Union High
School, Brandon, VT
ATTENDEES: 93 people signed in to the meeting. A number of the Town, Regional and State
officials/representatives that were in attendance are listed below:
Lynn Saunders Brandon Selectboard USC; BBSC; PBSC
Peg Flory Pittsford Selectboard USC; BBSC; PBSC
Richard Baker Brandon Selectboard USC; BBSC
Michael Balch Brandon Town Manager USC; BBSC
James O’Gorman Pittsford Town Manager USC; PBSC
Dolores Furnari Brandon BBSC
Senator Gerry Gossens State Senator
Mark Blucher Rutland Reg. Plan. Comm.(RRPC)
Susie Leonard RRPC
Judith Kmileck RRPC
Dan Peterson VTrans USC
Scott Newman VTrans
Chris Bean CLD USC; BBSC; PBSC
Jason Stone CLD
Jameson Paine CLD
USC Member, Rt. 7 Upgrade
Steering Committee
BBSC Member, Brandon Bypass
Steering Committee
PBSC Member, Pittsford Bypass
Steering Committee
1. Introductions
Chris Bean, CLD Project Manager, made general
introductions to those present.
2. Highlight
Purpose of Meeting
Chris
explained the purpose of the meeting was to update the public on the status of
the US Route 7 Upgrade Projects, explain the Pittsford and Brandon US Route 7
Bypass Scoping Studies, and obtain input on the purpose and need for bypasses
around each village.
3. Update of Us Route 7 Upgrade
Projects
Chris stated that the
overall US Route 7 Upgrade project has been segmented into six individual
projects. Conceptual Plans for 4 out of
6 projects will be submitted to VTrans for review by the end of this month. Plans for the remaining two projects will be
submitted by the end of February while the review is taking place. Once comments are received and incorporated,
the environmental and permitting documents will be developed and a formal
Section 502 Public Hearing will be scheduled.
The next step will involve Preliminary Plans, followed by Utility
Relocation Plans and Property Owner Meetings.
This step will signify the beginning of the Right-of-Way Process. See attached schedule for approximate
timetable.
4. Bypass Scoping Study Description
Jason Stone, CLD
Environmental Specialist, described the elements and purpose of a Scoping
Study.
A Scoping Study is an early
resource identification and coordination effort to identify natural, social,
and cultural resource constraints.
Coordination with State and Federal resource and permitting agencies is
initiated, and public input is sought to ensure that important considerations
are not overlooked. As this project is
a Federal undertaking, the coordination process will be in accordance with the
National Environmental Policy Act, as well as other Federal and State
regulations.
The purpose of this Scoping
Study is to determine whether there is justification to continue, through the
Environmental Impact Statement (EIS) process, with more detailed environmental
and design studies for a bypass around the Villages of Pittsford and/or
Brandon, Vermont. Stated another way,
this scoping study is being conducted to determine whether there are Bypass
Alternative Alignments that would be likely to be selected as the preferred
alternative during the formal EIS process.
The magnitude of natural and cultural resource impacts and the level of
public support for the potential bypasses will be important factors in this
determination.
5. Bypass Scoping Study Schedule
Chris described the anticipated schedule (see
attached schedule) for completing the Pittsford and Brandon Bypass Scoping
Studies.
Chris
explained that an Origin/Destination (O-D) Study was initiated by CLD in
October 2000 in order to determine where traffic was coming from and going to,
along the US Route 7 Corridor. Between
20% and 30% of northbound and southbound vehicles were randomly stopped and
asked to participate in the survey. The
survey was conducted just north of the Otter Valley Union High School in
Brandon and lasted approximately 12 hours.
The results of
the O-D Study have been summarized. A
general summary of the survey follows, although some of these results may
change slightly depending on the exact alignment of each Bypass Alternative:
-
More
than 3/4 of the vehicles surveyed would potentially use a Pittsford bypass;
nearly 2/3 would potentially use a Brandon Bypass; and more than half would
potentially use both;
-
Similarly,
more than 80% of trucks would potentially use a Pittsford Bypass; more than 60%
of trucks would potentially use a Brandon bypass; and nearly 50% of trucks
would potentially use both;
-
Pittsford
Bypass Opinion: 13% Opposed, 65% In Favor, 22% Did Not Know;
-
Brandon
Bypass Opinion: 12% Opposed, 68% In Favor, 20% Did Not Know;
-
Percent
Trucks Surveyed: 11% Northbound, 9% Southbound;
-
Nearly
2/3 of all trips were business/work related.
Jason updated the audience
on several of the CLD team efforts that have been completed or are ongoing:
·
Rutland Regional Planning
Commission (RRPC) Socio-Economic Assessment
The RRPC has been hired by
CLD to complete a review of socio-economic resources in the project area and to
determine the effects of a bypass on the economic condition of the area. The RRPC is currently obtaining baseline
data for both Pittsford and Brandon. At
this point, their report is approximately 75% complete.
·
Environmental Resource
Identification/Constraints Mapping
CLD has obtained mapping and
natural resource information from the Vermont Center for Geographic
Information, Inc. (VCGI) and the RRPC.
This information will help identify constraints or areas of limitations
that will be considered in the development of conceptual bypass corridors.
Resources that will be
reviewed include:
- Cultural Resources -
Individual Historic Properties - Historic Districts centered on the villages
- Social Resources -
Businesses, Recreational Properties
- Threatened and Endangered
Species
- Farmland Soils
- Forested Areas
- Hazardous Materials
- Archeological Resources – To
be provided by VTrans, using a Predictive Model
- Deer Yards and other
Habitats of Concern
-
Wetlands
and Surface Waters - Class II and III wetlands, Otter Creek, Neshobe River,
Furnace Brook, Sugar Hollow Brook, Jones Mill Pond and Jones Mill Brook,
·
Resource Agency Coordination
CLD has begun initial
correspondence with the US Army Corps of Engineers and several departments of
the VT Agency of Natural Resources to identify known resource concerns in the
project area.
8. Bypass Purpose and Need Statement
Discussion Items
·
Functional Characteristics
of US Route 7
Chris explained that the Functional
Classification of a roadway defines its purpose within the local, regional, and
national highway network. US Route 7 is
part of the National Highway System and is classified as a Rural Principal
Arterial Highway. The primary purpose
of this class of roadway is to move people and goods over long distances
between larger centers of population, as opposed to providing access to local
land uses, which are typically served by local roads.
Within
the project area, and especially in the Villages of Pittsford and Brandon, US
Route 7 currently serves dual purposes.
The highway accommodates local access needs, as evidenced by the
availability of on-street parking, numerous local intersections, and pedestrian
activity, and provides its intended rural principal arterial function of moving
people and goods. These uses are in
conflict; local access needs in the villages impede the mobility function of US
Route 7 as part of the regional and national network.
A 1996 VTrans study was conducted to assess
the sufficiency of this section of US Route 7.
Sufficiency ratings consider a highway's structural condition, safety,
and quality of service. This section of
US Route 7 was rated at or below 60, out of a best score of 100 points,
indicative of a poor or bad section of highway. This is unacceptable for a portion of the National Highway
System. The proposed upgrade projects
will alleviate the problem, but since these projects primarily address
operational and safety issues, they will not improve long-term level of service
performance within the villages.
Additional highway capacity is necessary to achieve this goal.
In order for US Route 7 to provide acceptable
levels of safety and efficiency for all modes of transportation, including
bicycles and pedestrians, it is necessary to expand, or otherwise improve the
existing highway facility, and reduce or eliminate the conflicts that arise
from the conflicting uses. CLD
Consulting Engineers, Inc. prepared a Scoping Report (April 2000) for VTrans,
for proposed improvements to the existing highway within the project area. A conclusion of the Scoping Report is that
traditional highway widening and intersection improvements could conceivably be
implemented on the existing highway alignment in the "corridor area"
between the villages. However,
substantial environmental (natural and social) resource constraints and
regulatory permitting issues were identified in the villages that would
preclude any proposal to significantly widen the highway through the villages
from being selected as the preferred alternative. Therefore, it is necessary to separate the local access uses from
the mobility function of the highway by providing a bypass roadway around the
villages. This view is supported by a
1994 Wilbur Smith Study, as well as a CLD Traffic Origin/Destination Study
conducted in 2000. These studies
concluded that at least 50% of passenger vehicle traffic and truck traffic
would use a bypass, depending in part on its exact location. Such high levels of traffic diversion
emphasize the conflicts inherent in the current uses of US Route 7 through the
villages, and stress that a bypass is the best long-term solution to satisfy
the functional and operational needs of the local, regional, and National
Highway System in this part of Vermont.
The purpose of this project is twofold. First, it is to preserve and improve the
Rural Principal Arterial Highway function of US Route 7 within the project
area, through the construction of a bypass(es). Shifting through traffic from the villages to a bypass(es) will
achieve the secondary project purpose, which is to enhance the highway's
ability to serve local community needs.
·
Quality of Life Issues
Both Pittsford and Brandon Officials desire
to increase pedestrian activity and encourage pedestrian dependant businesses
in order to preserve and enhance the feeling of community within the village
settings. Other related goals are to
improve the ability to access or cross US Route 7, to increase the ease of
motorists accessing intersecting roadways and business and residential drives,
to maintain or improve on-street parking, to improve opportunities for street
fairs, parades, etc. The project will
also reduce problems associated with noise and dust, such as the inability for
neighbors to socialize outside of their residences, and the need for residents
to frequently repaint their homes.
Chris presented a graphic that helped to
illustrate public comfort levels in relation to traffic volumes along US Route
7. The graphic was developed based on a
comfort level rating system created by the Two Rivers-Ottauquechee Regional
Planning Commission. As traffic volumes
increase along US Route 7, the comfort level of persons within the area
steadily decreases from “Happiness,” “Discomfort,” “Pain,” to “Severe Pain”
(see attached graphic). With the
introduction of a bypass, the traffic volumes on US Route 7 would decrease,
thereby increasing a person’s comfort level.
·
Other Benefits Derived from
a Bypass
- Constructing a bypass around
the villages would dramatically increase the design life of any of the US Route
7 Upgrade Projects within the village areas.
-
Air
quality, noise, and dust levels would be reduced in the villages.
9. Open Discussion
1.
A large number of OMYA trucks bring raw materials from the south of
Pittsford. These trucks also return to
southerly destinations. These vehicles
would only use a westerly bypass. They
would not use any other bypass.
In the development of
conceptual bypass corridors, linkage of state highways and critical local roads
such as Kendall Hill Road , a.k.a. the truck route, via interchanges or stubs
will be considered where feasible, to ensure that such vehicles, as well as
other large, through vehicles would divert to the bypass.
2.
The National Forest is located in the northeast corner of the project
study area. Will you show this on the
constraint mapping?
CLD has the bounds of the National
Forest in its GIS system and will display it on future mapping efforts.
3.
What is the commitment from VTrans for funding a bypass project? What is the priority of these projects?
Dan Peterson, VTrans: The
bypass projects are in the planning process at VTrans. Final costs are not known at this time
(depends on number of bridges, etc.).
The process right now is to determine the viability of bypasses in this
area so recommendations can be made to the Legislature.
4.
Is there any type of master plan that has been developed for the US
Route 7 Corridor?
Dan Peterson, VTrans: Not
aware of any US Route 7 Master Plan that has been developed.
5.
How will the bypasses affect plans to bring commuter trains from
Burlington to Rutland?
Dan Peterson, VTrans: Not
sure whether the bypasses will affect these plans.
Peg Flory: The State is
putting together a master plan for commuter and rail lines. Once this report is complete, we’ll have a
better idea of whether commuter rails will be used between Burlington and
Rutland.
6.
Tourists are important to this area.
The upgrade of US Route 7 is a band-aid fix. A bypass is needed.
The Steering Committees have
made it clear that US Route 7 upgrade work is necessary whether or not the
bypass is constructed. The improvements
are intended to help address existing deficiencies within the current US Route
7 Corridor.
7.
It is inconceivable that people still need to state the need for a
bypass. The $25 million is unnecessary
for the upgrade projects. If that money
is used for the upgrades, then no money will be left for the bypass projects.
Dan Peterson, VTrans: The
upgrade projects are scheduled to be constructed in the next 5 to 10
years. The bypass projects would
probably be built a minimum of 10 to 15 years from now. Funding may not be as much of an issue as it
would seem, due to the different timeframes.
8.
Improvements along US Route 7 would increase traffic speed in the
villages.
The proposed roadway
improvements actually narrow roadways and formalize traffic lanes in some
areas, potentially reducing traffic speed.
9.
I’ve talked to Scott Newman (VTrans) about proposed truck climbing
lanes on the US Route 7 upgrade project near VT Route 3. Concerned about the yellow house that would
be torn down.
Impacts to this property are
associated with the upgrade of US Route 7.
The plans are being developed with minimization of impacts to historic
structures as a priority. The property
and residence will be treated in accordance with the regulations of the
National Historic Preservation Act, and measures to minimize harm, including
appropriate historical recordation and other mitigation, will be undertaken.
10.
Worried about existing disruptions to businesses that are being caused
by increased traffic on US Route 7.
When do we accept the information that has been compiled and start
constructing a bypass?
As stated previously, the
bypass projects are in the early stages of study. Assuming the projects advance to construction, work would not
begin for at least 10 years. Traffic
control plans will be developed as part of the upgrade projects to minimize
disruptions to businesses.
11.
Lives out in the country. Does
not want a bypass near her property.
12.
Wants her town back. Bypasses
are necessary to restore the character and feeling of community within the villages.
13.
Does not want bypass, because he moved to the country to get away from
traffic.
14.
Many lives are threatened with the existing US Route 7. A bypass is needed.
15.
There has to be some way to expedite the process of building a bypass.
At this time, all pertinent
Federal and State environmental regulations have to be followed if a bypass is
to be constructed. This includes
completing the Bypass Scoping Studies to determine if a bypass is a viable
option.
16.
Is it possible to put the upgrade money towards the bypasses first and
then upgrade US Route 7 later?
The upgrade money is for the
entire US Route 7 corridor in this area.
The bypasses would still have to tie into the upgrade segments of US
Route 7.
17.
Should put people before wetlands.
The Governor has said that he doesn’t favor bypasses.
Peg Flory: Need to tell the
Governor that we want the bypasses.
18.
Scared to cross the street in Brandon Village. The only vehicles that seem to stop are the
OMYA trucks.
19.
Would the existing US Route 7 be renamed (to US Route 7A, 7B, etc.)
through the villages if bypasses were built?
They wouldn’t get maintained as well by the towns.
Dan Peterson, VTrans: It
would take an act of the Legislature to rename the routes, not VTrans.
20.
What do you need to get the project going?
Input like we are receiving
tonight that clearly states the public wants the bypasses.
21.
We need to watch the zoning of specific areas to act responsibly as a
community.
22.
Traffic has gotten so bad that choice is made to drive rather than
walk, feel unsafe walking.
23.
The fact that OMYA truck trips were limited during the Act 250 process
is evidence supporting the need for a bypass.
The meeting
adjourned at 9:20 p.m.
CRB:JAS:cww
Attachments
cc: US Rt.
7 Upgrade Steering Committee
Brandon Bypass Steering
Committee
Pittsford Bypass Steering
Committee
PROJECT SCHEDULE
Pittsford and Brandon
Bypass Scoping Studies
·
Perform
Origin-Destination Studies 10/2000 10/2000
·
Begin
Resource Agency Coordination 10/2000 10/2000
·
Begin
Individual Town Steering Committee Meetings (SCMs) 11/2000 11/2000
·
Develop
Draft Purpose and Need Statement 12/2000 1/2001
·
Joint
Public Informational Meeting - Local Concerns and Purpose and Need 12/2000 1/2001
·
Individual
Town SCMs - Present Constraints Maps 01/2001
·
Individual
Town SCMs - Alternatives Discussions 02/2001
·
Resource
Agency Meeting - Alternatives Discussions 02/2001
·
Individual
Town SCMs – Alternatives, Issues Discussions 03/2001
·
Joint
Public Informational Meeting - Alternatives Discussions 04/2001
·
Draft
Bypass Scoping Study Submittal 05/2001
·
Individual
Town SCMs - Review Bypass Scoping Study 03/2001
·
Joint
Public Informational Meeting – Present Study Conclusions 06/2001
·
Publish
Bypass Scoping Study 07/2001