M E M O R A N D U M

TO: File

FROM: Jason Stone, Environmental Specialist

DATE: March 18, 2002

RE: VTrans

Pittsford-Brandon NH 019-3(49)SC

CLD Reference No. 01-0370

Subject: Conceptual Plans Steering Committee Meeting

Location: Pittsford Municipal Building

Attendees: *Peg Flory Town of Pittsford

*James O'Gorman Town of Pittsford

*Hank Pelkey Town of Pittsford

*Michael Balch Town of Brandon

*Lynn Saunders Town of Brandon

*Richard Baker Town of Brandon

*Dan Peterson VTrans, Project Manager

Greg Riley VTrans, Planning Coordinator

*Chris Bean CLD

Jason Stone CLD

Bill Taranovich Pittsford Resident

Bob Wood Representative, District R-2

*Steering Committee Member

Notes From Meeting

  1. VTrans Historic Preservation Coordination

In order to complete the necessary historic preservation (Section 106) coordination, resolution must be reached on the issues highlighted below. Once outstanding issues are resolved, Duncan Wilkie - VTrans Archeologist, and Scott Newman - VTrans Historic Preservation Coordinator, can complete the Formal Comment Letters, which are necessary elements in the Categorical Exclusion Environmental Documents.

Fort Vengeance Monument Site Parking Area - Coordination with Taranoviches, Pittsford Historical Society

Jason Stone informed the Committee that CLD provided VTrans with a revised plan for a parking area at the Fort Vengeance Monument Site that meets the criteria established at the January 14, 2002, meeting. The revised plan shows the parking area located just to the north of the previous location. Duncan Wilkie will meet with the landowners (Taranoviches) and then with the Pittsford Historical Society to discuss the plan. Dr. Wilkie indicated that the meeting would take place soon.

Downtown Brandon Landscape Plans

CLD presented the landscape plans developed for Crescent Park and Brandon Central Square. Jason Stone and Chris Bean explained the details that have been revised or added based on the coordination that has taken place with CLD, the Steering Committee, Scott Newman - VTrans Historic Preservation Coordinator and Nancy Leary (representing the developers of the Howe-Scale Block project). The objective was to avoid discontinuity between the two projects where it is feasible to do so. The Committee approved of the plans, in general, and made the following comments and observations:

With regard to the landscape plans in general, Chris noted that it would still be possible for revisions to be incorporated into the project design. This may also happen elsewhere throughout the project area as a result of the Section 502 Public Hearing process.

  1. Conceptual Plans Submission and Section 502 Public Hearing Schedule Updates
  2. Chris informed the Committee that Revised Conceptual Plans for project Segments 1, 2 and 5 have been submitted to VTrans. He stated that CLD expects to submit the plans for Segment 6 by the end of March. Chris explained that there are issues that remain on project Segment 3 (studies on providing fish passage at Sta. 11+912) and Segment 4 (Fort Vengeance Monument Site parking area) that need to be resolved before plans can be submitted for those segments. Chris noted that CLD anticipates submitting plans for Segments 3 and 4 by mid-April. Dan Peterson added that VTrans has accepted the plans for Segments 1 and 2. He is awaiting the results of a culvert investigation at Sta. 19+710 in Brandon before accepting the Segment 5 plans, as the need to replace this culvert would result in natural resource impacts and affect the amount of property that would need to be acquired.

    Chris informed the Committee that a Section 502 Public Hearing for project Segments 1 and 2 has been set for Tuesday, May 14, 2002. Dan added that the "Skull Session," or dry run, is scheduled for Tuesday, April 30, at VTrans Headquarters. Meeting times were not set. Chris indicated that it should be possible to schedule Section 502 Public Hearings for project segment 6 for mid-June, and for project Segments 3, 4 and 5 for late June, 2002. Chris noted that CLD has completed the property owner research and had identified approximately 500 property owners that abut the overall project.

    Richard Baker asked whether it was the correct time to determine the priority for constructing the projects. Dan Peterson responded that such decisions should be made after the Section 502 Public Hearings. He added that project Segment 6 could advance ahead of the others as a municipally managed project administered through the VTrans Local Transportation Facilities Office if the Town is interested in pursuing that option.

  3. Changes to Roadway Slope Design, Station 7+100 ~ 7+160 - Project Segment 1
  4. Jason Stone informed the Committee of a recent change in the plans for project Segment 1. A retaining wall approximately 200 feet in length is now proposed to avoid impacts to Furnace Brook. Dan Peterson noted that VTrans Hydraulic and Environmental Staff favored making the change now as opposed to after the Public Hearing. Dan also noted that the wall would increase the overall project cost. The Committee did not object to installing a wall in this location.

  5. Video Inspections of Culverts on Project Segments P5 and P6
  6. These inspections are necessary to determine the structural integrity of two culverts (Sta. 19+710 and 21+890 in Brandon Village). The stone arch bridge over the Neshobe River will also be inspected. CLD has initiated landowner contacts and video inspections will be conducted soon.

  7. Structure Type Study for Sta. 11+912 Culvert
  8. Dan Peterson informed the Committee that CLD has submitted a Draft Structure Type Study for replacement and rehabilitation options for the culvert on project Segment 3 at Sta. 11+912. Dan gave a brief description of the options that CLD included in the study and the associated costs. Dan noted that the costs are subject to change somewhat. He explained that rehabilitating the culvert would cost about $100,000 and would not provide fish passage, while replacing it would cost about four times as much and would provide fish passage according to the design criteria specified by VTANR. Dan explained that once the study is final, it would be provided to VTANR, which will make its recommendation of its preferred option at this location. Peg Flory, Lynn Saunders and Bob Wood asked whether Ron Regan - Commissioner of VTANR Fish and Wildlife Department would be a party to the recommendation. Peg added that Mr. Regan had indicated to her that he would closely monitor coordination on this issue. Dan stated that he would notify the Committee once the final study has been forwarded to VTANR and asked that VTANR staff be given the opportunity to review the study before Committee members contact VTANR. The Committee agreed.

  9. Other Issues
  10. Cattle Pass at the Rasmussen Property

    Chris Bean asked whether consideration should be given for providing a cattle pass for this property. Chris pointed out that if the cattle pass was constructed in close proximity to the culvert at Sta. 11+912, there may be an opportunity to reduce construction related costs, especially if it is determined that the culvert should be replaced. After some discussion, it was agreed to proceed with the plans as currently proposed. It was pointed out that the landowners and/or the farm operators would have the opportunity to request a cattle pass during the Section 502 Public Hearing process.

  11. Next Meeting

The next US Route 7 Upgrade Steering Committee was set for Wednesday, May 22, 2002, from 4 - 7 PM, at the Pittsford Municipal Building.

 

JAS:jm

cc: Attendees Lynn Saunders C. Baird Morgan Alan Neveau

Mike Balch Dan Peterson Chris Slesar Ed Barna

Richard Baker Greg Riley Mark Blucher Dolores Furnari

Dennis Benjamin Susie Leonard Peg Flory Duncan Wilkie

Paul Conner James O'Gorman John Narowski Christopher Borstel

Hank Pelkey Scott Newman Gary Klinefelter Gerry Gossens

Frank Farnsworth Roy Newton Virginia Russell Kathleen Ryan