M E M O R A N D U M
TO: File
FROM: William P. Grace
NOTE: Review comments were solicited from Derry, Londonderry, FHWA, and NHDOT
on 7/25/01. Those comments that were
received have been incorporated.
DATE: July 17, 2001
RE: Derry-Londonderry
Exit 4A
Environmental Impact
Statement
CLD Reference No. 97-0209
SUBJECT: Combined
Local Administrative Oversight Committee (LAOC)/Technical Advisory Committee
(TAC) Meeting
LOCATION: CLD Office, Manchester, NH
ATTENDEES: *Carol Granfield Town
of Derry
*Jim MacEachern Town of
Derry
*Ed Boutin, Esq. Town of Derry
*Troy Brown Town
of Londonderry
**George Sioras Town of Derry
**Janusz Czyzowski Town of Londonderry
**Butch Waidelich FHWA
**Bill O’Donnell FHWA
**Jeff Brillhart NHDOT
Bill Cass NHDOT
Marc Laurin NHDOT
Roberta Robie Derry CATF
Member
Christopher Bean CLD
Bill Grace CLD
Paul Konieczka CLD
Jameson Paine CLD
*LAOC Members
**TAC Members
LAOC members unable to
attend: Bob Carr, Esq. Town of Londonderry
Andrew Greco Town of
Londonderry
TAC members unable to
attend: Moni Sharma SNHPC
Items
discussed:
1. Meeting Purpose
Chris Bean explained that the two basic
purposes of the meeting were to discuss revisions to the proposed new
alternatives and define the direction of the project.
2. Possible
Alternatives ‘G’ and ‘H’
At the last combined
TAC/LAOC Meeting held on 5/22/01, CLD was asked by the Towns to modify the
design of Alternatives G and H to minimize right-of-way acquisitions to the
extent practicable. Chris Bean
presented the modified design using 100-scale plans. These alternatives would begin on NH Route 102 (Broadway) just
east of the Exit 4 ramps and require modifications to the Broadway/Londonderry
Road intersection, providing a primary through movement for traffic along
Londonderry Road and a secondary movement for traffic continuing down
Broadway. This intersection would be
signalized. The initial pre-conceptual
design for the Londonderry Road/Broadway intersection called for the
acquisition of several residences/businesses on the east side of Londonderry
Road. The modified design results in
fewer acquisitions by shifting the widened Londonderry Road towards the
west. Also, the alignment was shifted
to avoid impacting three homes on Madden Road.
Alternative G now matches into Alternative A and Alternative H matches
into Alternative B, north of Ash Street.
A preliminary environmental impact matrix that listed the remaining
alternatives (A, B, C, and D, as well as Alternative F, which is the minor
upgrade of NH 102) and the two new alternatives (G and H) was distributed for
discussion. (The no-build alternative
would also be carried through the Draft EIS.)
Both Alternatives G and H
would require the expansion of Londonderry Road to five lanes and would involve
substantial right-of-way impacts to homes and businesses along Londonderry Road
and NH Route 102. These include the
Derry Plaza, which contains seven businesses.
Access to properties on the
east side of Londonderry Road appears to be feasible by using the bypassed
section of that road to provide access to Broadway. Access for commercial properties on the south side of Broadway
may be difficult. One option would be
to use the bypassed section of Broadway to provide access via Ela Avenue or St.
Charles Street. Another option may be
to allow only right turns in and out of these businesses (currently gas
stations).
A question was raised
regarding the shifting of Londonderry Road towards the east near Ash
Street. CLD explained that this was an
attempt to minimize property impacts on the west side of Londonderry Road. There are also engineering concerns
regarding the widening of the Londonderry Road/Ash Street intersection, which
would require a wider bridge over I-93.
Bill Cass noted that the I-93 widening project would likely impact the
properties on the west side of Londonderry Road. Therefore, a shift towards the west should be considered if this
alternative moves into the detailed design phase.
Paul Konieczka explained the
changes in the “Purpose and Need” section of the environmental impacts
matrix. Under the heading of “Economic
Development,” the alternatives were labeled as having “direct,” “slightly
improved,” or “indirect” interstate access to the industrial/commercial zoned
lands between I-93 and the Derry Industrial Park. Also, a new traffic volume location (ADT) for a location east of
I-93 and west of Londonderry Road has been included in the matrix under the
‘Purpose and Need’ section for comparison purposes. The results of the traffic modeling showed Alternatives G and H
were the least effective alternatives (5-7% reductions) for removing traffic
from downtown Derry, and providing indirect interstate access for the
commercial/industrial land in both Derry and Londonderry.
Alternative G would require
the acquisition of 21 buildings (10 residential and 11 commercial), impact 1.3
acres of wetlands, 11 historic properties including 6 buildings, and would cost
approximately $13.4 million, including engineering design, construction and right-of-way. One of the acquired commercial buildings
would be the Derry Plaza, which contains seven businesses.
Alternative H would require
the acquisition of 24 buildings, 13 residential and 11 commercial, impact 4.2
acres of wetlands, 4 historic properties (no buildings), and would cost
approximately $15.5 million for design, construction and right-of-way. This alternative would also require the
acquisition of the Derry Plaza.
CLD recommended continuing
the studies of Alternatives A, B, C, D, and F, as well as the no-build option,
and discontinuing Alternatives G and H.
Alternatives G and H provide little traffic reduction on Broadway, and
would have substantial right-of-way impacts, but do provide access, albeit
indirect, to the industrially/commercially zoned lands.
3. Comments and
Concerns for Alternatives G and H
FHWA
Bill O’Donnell felt that
although the traffic model information for the location west of Londonderry
Road may be useful, he does not feel that this short section of NH 102 is critical
relative to the project ‘Purpose and Need’ and should be removed from the
matrix. Butch Waidelich agreed that it
may not be critical to the purpose and need; however, it is an impact that
would still be considered when comparing alternatives. CLD explained that the traffic volumes along
this stretch would be substantial (close to 40,000 vehicles per day) if
Alternatives G or H were pursued, and there is serious congestion in that area
at the present time. These projected
heavy volumes will dictate the amount of access control required. For now, this traffic evaluation point will
remain in the matrix.
Bill O’Donnell noted that
there was not much difference between Alternatives C or D, and G or H, relative
to the reduction of traffic volumes on Broadway. However, Alternatives G and H do provide some traffic reduction
along Broadway and do serve the industrial lands east of I-93. Later in the discussion, Bill agreed that public
input should be solicited before dismissing Alternatives G and H.
Butch Waidelich noted that
the remaining lands along Londonderry Road, after the buildings were removed,
could be consolidated and possibly resold for new development to compensate for
the commercial business impacts.
Butch explained that NEPA
regulations require that the natural, socio-economic, and cultural environments
need to be considered. The new
alternatives have serious impacts to the socio-economic environment. If these alternatives and their impacts are
considered reasonable, then they should be carried forward for further
study. The Towns need to collectively
decide if these impacts are reasonable and acceptable. At this point, the Towns appear to be saying
that the impacts are not acceptable.
These decisions need to be well-documented in the Rationale Report and
in the Draft EIS.
Londonderry
Janusz Czyzowski noted that
the largest single expense of Alternatives G or H would be right-of-way costs,
and if the remaining lands could be consolidated and resold this could result
in a lower overall cost. However, with
the revised design, and the proposed I-93 widening, there may not be enough
room to effectively consolidate the properties.
Troy Brown asked if
Alternatives A or B were selected, could improvements on NH 102 at Exit 4 and
west of Exit 4 also be implemented. The
response was that this might be practicable.
However, the I-93 widening project will also be considering improvements
to Exit 4 and to NH 102. Impacts west
of Exit 4 are not part of the “Purpose and Need” for this project. Coordination of the two projects will
continue.
Troy felt that the
socio-economic impacts of Alternatives G and H might be unacceptable. At the last TAC/LAOC meeting, the impacts
were viewed as potentially acceptable.
Janusz felt that they provided some traffic benefits and improved access
to industrial lands.
NHDOT
Jeff Brillhart commented
that the NHDOT would be responsible for any improvements to Exit 4. He also felt that the new designs of the new
alternatives have reduced impacts to some of the properties along Londonderry
Road and Madden Road. He felt the new
alternatives are still viable, and the Towns would incur substantial risk of a
legal challenge if these alternatives were dropped at this point. He reminded the group that the NEPA process
requires substantial public input, and he recommends another Public
Informational Meeting to discuss these alternatives. Jeff has been involved with many EIS projects, and it has been
his experience that the impacts such as those associated with Alternatives G
and H are not insurmountable. The
environmental impact matrix shows little difference among the remaining
alternatives, particularly relative to reducing traffic congestion on Broadway. Therefore, public input is even more
critical.
Derry
Carol Granfield stated that
Derry and Londonderry want to move this project forward as expeditiously as
possible. Informed decisions regarding
the remaining alternatives to be studied further need to be made conclusively. However, the two towns are funding this project
on their own and resources are limited.
Carol noted that
Alternatives G and H do not provide enough traffic reduction on Broadway and
should not be studied further. The
Towns need to determine what is reasonable to study.
Ed Boutin noted the consolidation
of remaining properties on Londonderry Road might result in access issues that
may diminish the effectiveness of that road.
He also noted that access to the industrially/commercially zoned lands
east of I-93 has always been a secondary focus of this project, but access to
lands along Londonderry Road has not been.
Ed asked if Alternatives G
and H were studied further, is it likely that any new information would arise
that would possibly affect the decision.
CLD responded that the additional studies, including more detailed
impacts to air quality, noise, field studies of natural and cultural resources
and further traffic analyses, are not likely to provide such information.
George Sioras reminded the
group that the original intent of this project was to relieve traffic
congestion on NH 102 in Derry and Londonderry and to maintain the integrity of
Exit 4. NHDOT modified Exit 4 in the
late 1980’s and further improvements are expected with the proposed widening of
I-93. The industrial land east of I-93
became a secondary issue. George also
noted that NHDOT is working with Derry and Londonderry to study possible
widening of NH 28 near the Wal-Mart.
Also, George noted that there is increasing traffic to and from Chester
and Sandown, and there have been many new subdivisions recently approved,
especially in Chester.
Jim MacEachern stated that
there have been numerous public meetings and the consensus was to move forward
with Alternatives A, B, C, D and F. He
felt that the TAC and LAOC have completed sufficient studies of Alternatives G
and H and could comfortably discontinue further studies.
Roberta Robie felt that the
results from the SNHPC traffic model show that the new alternatives would not
divert much traffic from Broadway. Many
vehicles would continue to use Broadway not only to access the downtown area,
but also to continue easterly along NH 102.
Roberta also noted that most of the impacts and the potential
socio-economic and traffic benefits of Alternatives G and H would occur in
Londonderry. She reminded the group
that the primary goal of the project is to relieve traffic congestion on
Broadway. Economic development is
secondary.
4. Removing Alternatives
Questions were raised as to
why further review is needed for Alternatives G and H. After some discussion, it was agreed that a
series of meetings to discuss the elimination of Alternatives G and H would be
held in the near future. These will
include a meeting with the Resource Agencies, the Derry Town Council, the
Londonderry Town Council, and a Public Informational Meeting.
Chris Bean stated that the
Towns had requested the elimination of Alternatives C and D from further study
to save time and reduce costs. FHWA had
suggested that CLD carefully document the rationale for eliminating those
alternatives and submit that request to FHWA for consideration. However, CLD has analyzed the elimination of
these alternatives and feels that there is insufficient evidence to clearly
document reasons for eliminating Alternatives C and D, and also insufficient
public support or non-support for these alternatives.
Although there has been some
discussion regarding the elimination of the so-called bypass alternatives (B
and C). FHWA felt these alternatives
are still reasonable and should continue to be studied. The Towns would encumber a greater level of
risk if these alternatives were dropped from further study. Legal challenges could be expected. Jim MacEachern stated that the Derry Town
Council has voted to support Alternative B if it were truncated at NH Route
28. CLD noted that this alternative may
result in substantial traffic complications and has not yet been given full
consideration. Butch noted that this truncated
alternative can be investigated further or reconsidered later in the NEPA
process without having to analyze an entirely new alternative, since it is part
of an alternative already identified
Some discussion centered on
the origination of alternatives G and H.
It was noted that similar options were discussed in the 1980’s. The current recommendation came from a
Londonderry Councilor during the January, 2001, Public Informational Meetings.
5. Next Steps
a)
Resource Agency Meeting
CLD will meet with the
Resource Agencies at the next NHDOT monthly meeting (Wednesday, July 18, 2001)
to present Alternatives G and H and recommend that those two alternatives be
removed from further consideration.
Alternatives A, B, C, D and F, as well as the no-build option, would
remain for further in-depth environmental review (carried through the DEIS) and
design work.
b)
Town Council Meetings
CLD will present the revised
design and impacts analyses for Alternatives G and H to the Derry Town Council
and to the Londonderry Town Council with the recommendation for no further
study of these alternatives. An
official letter from each Town Council will be requested. Butch Waidelich pointed out that the local
officials’ endorsement of a particular alignment should only be used as input
for the DEIS. It should not be
considered as selection of a preferred alternative at this time. The Derry Town Council meets on the first
and third Tuesday of each month, and the Londonderry Town Council meets on the
first and third Monday of each month.
Potential dates for Derry were 7/24, 8/7, or 8/21. Potential dates for Londonderry were 8/6 or
8/20.
c) Public Informational
Meeting
After some discussion, it was determined that
one joint public meeting, given appropriate announcement in local newspapers
and on local cable access channels, should be held to notify the public that
Alternatives G and H have been analyzed and are not being proposed for further
study and announce that Alternatives A, B, C, D, and F will be carried through
the DEIS. The meeting will be held in
Derry in September.
d) Public Notification
The Towns will notify abutters along the new
proposed alternatives (G and H), as well as the other alternatives to be
studied further (A, B, C, D and F), of the Public Informational Meeting
individually by letter.
e)
Amendment Request
CLD will prepare an amendment
request to cover additional out-of-scope tasks associated with the new
alternatives and submit it to the Town Managers of Derry and Londonderry.
The meeting adjourned at
12:40 PM.
If the above notes do not
agree with your recollection of the meeting, please advise this office within 5
business days of receipt.
CRB:WPG:cww
cc: Technical
Advisory Committee (TAC):
Derry: George
Sioras, Alan Swan, Doug Rathburn
Londonderry: Andre Garron and Janusz Czyzowski
FHWA: Bill O’Donnell,
Butch Waidelich
NHDOT: David J. Brillhart and Marc Laurin
SNHPC: Moni Sharma
Local
Administrative Oversight Committee (LAOC):
Carol
Granfield Derry Town Administrator
James
MacEachern Derry Town Councilor
Edmund
Boutin, Esq. Derry Counsel
Troy
Brown Londonderry
Interim Town Manager
Andrew
Greco Londonderry
Town Councilor
Robert
Carr, Esq. Londonderry Counsel
Citizens Advisory Task Force
(CATF):
Derry: Londonderry:
George Sioras Troy
Brown
Albert
Doolittle Jim Anagnos
Roberta
Robie Eugene
Harrington
Jack
Dowd Jennifer
A. Sollars
Barbara
Concannon Gerry Shuck
Frank
Mazzuchelli Rep. Sherman
Packard
Suzanne
Regali
Project
Team
Victoria Bunker Lynne
Monroe (Preservation Company) Bruce
Mayberry