M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: May 21, 2001
RE: VTrans
Pittsford-Brandon NH
019-3(49)SC
CLD Reference No.
00-0219, 00-0248
SUBJECT: US
Route 7 Upgrade Steering Committee Meeting
LOCATION: Pittsford Municipal
Building
ATTENDEES: *Peg Flory Town of
Pittsford
*James
O’Gorman Town of Pittsford
*Hank
Pelkey Town
of Pittsford
*Mike
Balch Town of
Brandon
*Lynn
Saunders Town of
Brandon
*Richard
Baker Town of Brandon
Roy M. Newton Brandon-Pittsford
Reporter
Ed Barna Rutland Herald Reporter
Peg Armitage Rutland Business Journal Reporter
Mark Germanowski Rutland Regional Planning Commission
*Dan
Peterson VTrans,
Project Manager
Scott Newman VTrans,
Historic Preservation Coordinator
Greg Riley VTrans
Planning Section
*Chris
Bean CLD
Wayne Husband CLD
Jason Stone CLD
*Route
7 Upgrade Steering Committee Member
MEETING
NOTES
1. Conceptual
Plans Submission Schedule/Comments Review Meeting
Chris updated the Committee
on the Conceptual Plans submission schedule.
Plans for Project Segment 5 of 6 were submitted today, prior to this
meeting, leaving Project Segment 3 of 6 as the only segment for which an
initial plan submission has not been made.
It is anticipated that plans for Project Segment 3 of 6 will be
submitted by the end of May, 2001.
Chris explained that
CLD is in the process of resolving issues that have come out of the Comment
Review Meetings held thus far. He also
noted that a Comment Review Meeting to review Project Segments 1 of 6 and 2 of
6 is scheduled for June 1, 2001, at VTrans Headquarters in Montpelier, from
9:00 AM until noon. Jim O'Gorman
indicated that he would attend, as these segments are both within
Pittsford. Dan Peterson added that he
has received some comments regarding the Project Segment 1 of 6 and 2 of 6
plans, but has not as yet heard from the VTrans Highway Design and Structures
Sections. Dan felt that these comments
would be forthcoming. Dan also
mentioned that Gary Dubray would likely be the VTrans Project Manager for the
project segments that will not be municipally managed. Dan anticipates receiving comments from Gary
as well.
Chris Bean asked that
the Committee review all of the Project Segment plans, and give special attention
to areas where informal parking could be replaced, if that is determined
appropriate by the Committee. It was
the Committee's general opinion that the provision and replacement of parking
has been handled appropriately thus far.
2. Property Owner Meeting/Northerly Project
Extension
Earlier today, Chris
Bean, Wayne Husband, Jason Stone, Mike Balch, and Bruce Rounds met with Jim
Bourne (owner of Brandon Auto Sales) and his attorney to discuss the
improvements proposed along his property's US Route 7 frontage, and the effect
on access and circulation. The proposed
access control via a 1.8 m (6.84 ft) wide curbed island, would limit access to
two drives, each 10.5 m (34.4 ft) wide.
Mr. Bourne suggested widening the northerly drive and shifting its
location several meters to the south, to allow continued access to all three of
his garage bays facing US Route 7, as well as access for his northerly display
area. This would cause a reduction in
width of the southerly drive, but this was acceptable to Mr. Bourne. Chris and Wayne agreed it appeared as though
a concept could be developed that would incorporate the suggested revisions and
still comply with VTrans guidelines. The
Steering Committee's consensus was to proceed with the revised access plan. CLD will prepare a sketch plan of the
revision and provide it to the VTrans Utilities and Permits Section (Don
Gilman) for review. CLD will also
request that the modifications made by the Quick Mart/McDonald's property
developer would match CLD's proposal in the area.
3. Surplus
Material Disposal
Jason Stone updated
the Committee with regard to potential disposal sites for the surplus materials
generated by the Upgrade Projects. Greg
Markowski, of Markowski Excavating, has indicated that his property located on
US Route 7 in south Brandon has sufficient space for the storage of the
estimated total volume (500,000 m3 or 650,000 yd3) of
concrete and soil materials. He also
indicated that he is seeking the necessary permits to operate a concrete
recycling facility. He asked whether
recycled concrete could be used in the construction of the new highway. Jason responded that the recycled material
may be suitable for use as structural fill, assuming it meets the appropriate
specifications or if a special provision is made for its use. However, VTrans would not likely require the
construction contractor to use that recycled material.
CLD will list the
Markowski property as a potential surplus material disposal site in the
Environmental Documentation. Its
proximity to the project area and the fact that no Town roads would be traveled
to haul materials there are positive elements in its consideration. VTrans will not, however, require the
construction contractor to use that site, nor will it specify the eventual site
to be used. It is up to the contractor
to locate appropriate sites and obtain the required clearances. Per an agreement between VTrans and VTANR,
permitting issues associated with the disposal site are independent of the
projects.
4. Mailbox
Locations in Pittsford Village
Peg Flory indicated
that there is no real progress on this issue.
The idea of locating mailboxes at the back side of the proposed
sidewalks has been discussed with the Post Office, and the Post Office has not
responded negatively as yet. This
option would allow for faster on-foot delivery than would be possible if
delivery personnel had to make delivery at the doors of residences.
5. Act 250 Legislation
Peg indicated it would
be very unlikely that the Act 250 legislation, exempting roadway projects that
limited impacts to land within 50 feet of centerline, would be acted on during
this session.
Chris noted that these
projects were presented to the Environmental Board and added that a second
presentation to the Board will be made in the Preliminary Design phase, as
impacts are better defined.
6. May
24 Meeting With VTrans and VTANR Stream Alteration Engineer
A field visit to
review proposed box culvert and structure improvements is scheduled for
Thursday, May 24, beginning at 9:00 AM.
Attendees will meet at JR's Restaurant in Pittsford on US Route 7, and
will include Dan Peterson, Craig Keller and Mike Tuttle of VTrans, Fred
Nicholson of VTANR, Lisa Martin, Ed Chase and Jason Stone of CLD, and Hank
Pelkey of the Committee.
The purpose of the
field review will be to make a determination whether to replace or extend
culverts and structures to accommodate the proposed improvements. If structures are to be extended, the issue
of minimizing stream relocation impacts by extending the structure on a skew
will be discussed. Where the aquatic
habitat would indicate it is appropriate, and where structures are to be
replaced, the issue of implementing a more "fish-friendly" structure
will be discussed. Owners of properties
adjacent to the culvert locations were identified, and will be contacted prior
to the field meeting by Committee members, to alert the landowners of the
purpose of the field visit.
7. Landscape
Architecture, Traffic Calming, Pedestrian Issues, etc.
Wayne Husband
summarized the comments and suggestions received from CLD's subconsultant,
Kathleen Ryan, and asked for the Committee's input. With regard to replacing informal parking with formalized
parallel parking, the Committee 's consensus was that this issue was being
addressed appropriately in the plans as submitted. The Committee recognizes the need to maintain adequate parking in
the villages to sustain businesses, but does not want to promote expanded
parking outside those areas. Such
requests could be addressed later, in the Public Hearing process, if property
owners desired expanded formalized parking.
Mike Balch noted that
Brandon has completed a parking study, though the final report needs to be
written, and suggested that the findings would perhaps be useful to Kathleen
Ryan.
With regard to green
belts and other streetside appurtenances, Chris Bean explained that such
features will be incorporated into the plans where feasible, and added that
coordination with Scott Newman, VTrans's Historic Preservation Coordinator is
also necessary. A field visit will be
scheduled soon, to review streetside property impacts.
With regard to the
proposed 11:4 typical adjacent to head-in parking in Brandon, it was the
Committee's consensus that this width is not excessive, given the high traffic,
bicycle, and pedestrian volumes, and considering the high percentage of large
trucks. Wayne added that the
substandard horizontal alignments through the village areas could result in large
vehicles encroaching on the shoulders and opposing travel lanes if less than an
11:4 is used.
With regard to traffic
calming measures, Wayne and Chris explained that, as proposed, the project
would provide some level of calming.
The addition of curbing and lessening of paved area will achieve a
narrowing effect that would tend to slow traffic. Scott Newman added that streetside trees or other plantings,
street furniture, and other amenities that suggest the movement or presence of
people in the streetscape would enhance the calming effect.
8.
Planning for the Upcoming 502 Public Informational
Meeting
Chris
explained that separate 502 Public Hearings would be held, one for each
town. Dan Peterson added that the 502
Hearing Process must be adhered to in the acquisition of property by condemnation. These Hearings are targeted to occur by the
end of September, 2001. CLD will
investigate options for meeting sites.
9.
Other Issues
·
Fort Vengeance Monument Site - Avoidance Alternatives
As
it stands, the Site's easterly National Register Eligible boundary coincides
with the easterly edge of the US Route 7 pavement. Duncan Wilkie has requested that LBA conduct further testing of
the easterly roadway slope in this area, to determine the depth of prior
disturbance, and how it relates to archeological deposits. That information will have some bearing on
the final delineation of the Site's boundary, and will also affect CLD's
development of alternatives to avoid the site.
CLD will begin to develop such alternatives when the Site's boundary has
been fixed.
·
Next Meetings
The
next US Route 7 Upgrade Steering
Committee Meeting is scheduled for Monday, August 6, 2001, from 4:00 - 7:00
PM, at the Brandon Fire Station.
The
next Brandon Bypass Steering Committee
Meeting is scheduled for Monday, July 23, 2001, from 4:00 - 6:30 PM, at the
Brandon Fire Station.
The
next Pittsford Bypass Steering Committee
Meeting is scheduled for Wednesday, July 25, 2001, from 4:00 - 6:30 PM, at
the Pittsford Municipal Building.
CRB:cww
|
cc: Lynn Saunders |
Dan
Peterson |
Chris
Slesar |
Ed
Barna |
|
Michael Balch |
Greg
Riley |
Mark
Blucher |
Roy
Newton |
|
Richard Baker |
Dennis
Benjamin |
Mark
Germanowski |
Frank
Farnsworth |
|
Dolores Furnari |
Duncan
Wilkie |
Susie
Leonard |
Virginia
Russell |
|
Peg Flory |
John
Narowski |
Judith
Kmileck |
Sen.
Gerry Gossens |
|
James O’Gorman |
Scott
Newman |
Chris
Borstel |
Harry
McKinlay |
|
Hank Pelkey |
Alan
Neveau |
Gary
Klinefelter |
|
|
C. Baird Morgan |
Paul
Tober |
Kathleen
Ryan |
|