M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: May 21, 2001
RE: VTrans
Pittsford and Brandon
US
Route 7 Bypass Scoping Studies
CLD Reference Nos.
00-0215 and 00-0216
SUBJECT: Public Informational Meeting
LOCATION: Otter Valley Union High
School, Brandon, VT
ATTENDEES: 48 people signed in to the meeting (approx. 75 - 80
attended). A number of the Town,
Regional and State officials/representatives that were in attendance are listed
below:
Lynn Saunders Brandon Selectboard USC; BBSC; PBSC
Peg Flory Pittsford Selectboard USC; BBSC; PBSC
Richard Baker Brandon Selectboard USC; BBSC
Michael Balch Brandon Town Manager USC; BBSC
James O’Gorman Pittsford Town Manager USC; PBSC
C. Baird Morgan Pittsford PBSC
Dolores Furnari Brandon BBSC
Hank Pelkey Brandon Selectboard USC, BBSC
Mark Blucher Rutland Reg. Plan. Comm.(RRPC)
Paul Conner RRPC
Dan Peterson VTrans USC
Scott Newman VTrans
Greg Riley VTrans
John Narowski VTrans
Steve Sease VTANR
Rob Sikora FHWA
Chris Bean CLD USC; BBSC; PBSC
Jason Stone CLD
Wayne Husband CLD
Ed Barna Rutland Herald Reporter
Roy Newton Brandon-Pittsford Reporter
Peg Armitage Brandon Business Journal Reporter
USC Member, Rt. 7 Upgrade
Steering Committee
BBSC Member, Brandon Bypass
Steering Committee
PBSC Member, Pittsford Bypass
Steering Committee
1. Introductions
Chris Bean, CLD Project Manager, began the
discussion and made general introductions to those present. Chris mentioned that the information
presented at this meeting would also be available on CLD's website found at
www.cldengineers.com.
2. Highlight
Purpose of Meeting
Chris
explained that the purpose of the meeting was to update the public on the
status of the US Route 7 Upgrade Projects and Pittsford and Brandon Bypass
Scoping Studies, and to obtain public input on whether the Bypass Scoping
Studies should be advanced into the formal Environmental Impact Statement (EIS)
process.
Chris
explained that CLD has coordinated with Bypass Steering Committees from both
communities, as well as the public and the regulatory and permitting agencies,
in the development of conceptual bypass corridors around both of the
Villages. CLD has also tabulated the
associated impacts to various natural and social resources in an impact
matrix. Chris explained that while the
conceptual corridors are not alignments proposed for construction, they do
provide a reasonable estimation of the environmental impacts of constructing
bypasses around the Villages within the project area. This "order of magnitude" assessment of impacts, as
well as input from the public and the regulatory and permitting agencies, will
be the basis for VTrans's and FHWA's decision of whether to proceed with an
EIS.
3.
Steve Sease, Director of
Planning - VT Agency of Natural Resources (ANR)
Mr.
Sease explained that ANR is a multi-faceted State agency, comprised of Fish and
Wildlife, Forests and Parks, and Environmental Conservation Departments. He noted that ANR has jurisdiction over
state listed threatened and endangered species, and issues permits for impacts
to surface waters and wetlands. He then
briefly explained his Agency's role in the project development process, and
indicated that ANR is willing to assist the communities in identifying natural
and social resource impacts and concerns, and developing strategies to minimize
and mitigate impacts. Mr. Sease stated
that his Agency would generally favor shorter bypass alignments over longer
ones, as shorter alternatives would logically incur lesser environmental
impacts. Mr. Sease closed by stating
that ANR and VTrans are partners that work together to develop projects that
serve the public's transportation needs while preserving the natural
environment.
4. Update of US Route 7 Upgrade
Projects
Chris explained that the
overall US Route 7 Upgrade project has been segmented into six individual
contracts and gave a general description of the proposed improvements.
Conceptual Plans for the 6
contracts will soon be submitted to VTrans for review. Once comments are received and incorporated,
the environmental and permitting documents will be developed. A formal Section 502 Public Hearing is
targeted for Fall, 2001. Next steps
will involve Preliminary Plans, followed by Utility Relocation Plans and
Property Owner Meetings. This step will
signify the beginning of the Right-of-Way Process.
5. Bypass Scoping Study Schedule
Chris stated that the Draft Bypass Scoping
Study Report will be prepared and the findings presented to the public at
another Public Informational Meeting, currently targeted for September,
2001. After a public comment/input
period, the report would then be finalized and submitted to VTrans and
FHWA. These agencies will then decide
whether to proceed with an EIS.
6. Conceptual
Corridor/Impact Matrix Description
Chris described the conceptual corridors,
stating that they are essentially 150-foot wide bands. They are a reasonable estimation of the
impact footprint associated with a two-lane roadway, with truck climbing lanes
where warranted. Chris described the
12-foot lane, 8-foot shoulder typical, and indicated that the intersections
have only been considered at major intersecting roadways, such as VT Routes 3
and 73, and Kendall Hill Road, a.k.a. the Truck Route. Other local or Town roadways would not be
given access to the bypass. Chris noted
that limiting access to a bypass would reduce the potential for secondary, or
"sprawl" impacts along the local roadways and within the project
area.
7. Public Input/Open Discussion (Questions
are in Italicized Bold, Responses are in Normal Type)
1.
Do structures impacts account for residences or buildings that are not
directly impacted - has there been any consideration for proximity impacts?
When estimating the number
of impacted structures, impacts were first calculated using the 150-foot
corridor band, plus a 50-foot offset on each side (for a total of 250
feet). This was done to take into
account "near misses," as the structure location data only provided
"point locations" for structures.
The structures impacts were artificially inflated by this method,
especially where the conceptual corridors match in to existing US Route 7 and
cross other roadways. Structures
impacts were refined using aerial photographs with the conceptual corridors (150-foot
width) superimposed. At this stage,
direct impacts to structures were noted, as were other factors such as access
and proximity impacts. It is possible
that property and structures that are not directly impacted would be acquired
due to proximity impacts, and then re-sold after the project was complete.
2.
Is there information available that documents the effects of bypasses
on similar communities?
Mark Blucher, of the Rutland
Regional Planning Commission, stated that he did not have that information at
the meeting, but would provide it for those interested. He summarized that his understanding, based
on the information he has seen, is that communities do very well after bypasses
are constructed. Chris Bean noted
businesses that rely heavily on through traffic may be negatively
affected. Such businesses may change
hands to better suit the local needs.
3.
What criteria were used in the identification of wetlands?
The wetlands information
depicted on the plans was obtained from the Vermont Center for Geographic
Information, as well as VTANR. In
general, three criteria are necessary for determining the presence of a
wetland: hydric soils, hydrology, and wetland vegetation. It should be noted that only Class I and
Class II wetlands are depicted on the mapping, and this is customary for
planning level studies.
4.
It appears as though Corridor BE would impact Pine Hill Cemetery.
It should be stressed that
the conceptual corridors are not alignments proposed for construction. If, in a future design study, an alignment
similar to Corridor BE were proposed, it would likely be designed to avoid the
cemetery.
5.
It appears as though a bypass could be constructed, following the
existing Country Club Road - has this been considered?
As the bypass has been
considered as a limited access facility, no driveway connections to the new
roadway would be allowed. Therefore,
all of the residences along Country Club Road would be impacted. For this reason, such an alternative was not
pursued.
6.
A westerly bypass around Pittsford would seem to benefit the OMYA
facility. Has OMYA lobbied for any of
the alternatives?
We are not aware of any
preferences expressed by representatives of OMYA.
7.
It appears as though Corridor PW would impact the landfill.
See response to number 4,
above. If such an alternative were to
be designed, efforts to avoid impacts to the landfill would be made. If impacts to the landfill were unavoidable,
the facility may be relocated.
Appropriate investigations would be undertaken to ensure that the new
roadway did not cause the displacement or migration of contamination associated
with the landfill.
8.
It appears as though the deer wintering areas are undermapped.
The environmental
constraints mapping was developed using the most current information
available. The constraints maps were
reviewed by the Natural Resource Agencies, and some adjustments were made. Actual field verification of all of the
information was not possible, nor appropriate for this level of study. It is possible that the mapping of certain
resources would be further adjusted based on field surveys. Such surveys would be done during the EIS
process, should the study move ahead.
9.
It has been stated that three lanes will be proposed where
truck-climbing lanes are warranted. How
many miles of three-lane roadway will be necessary?
Truck climbing lanes would
be constructed where warranted. The
length of three-lane roadway to be constructed would be dependent on the actual
location of a bypass alignment. Without
knowing that location, it is not possible to estimate the length of need for truck
climbing lanes.
10.
Concern was expressed over the noise and visual impacts to the villages
associated with a short bypass.
11.
If the Upgrades will not be constructed for at least several years, how
can we determine the need for bypasses now?
The Upgrade Projects do not
address the need for bypasses. The
Upgrades would not address the conflicts between through traffic and local
traffic in the Villages.
12.
Brandon is more affected by OMYA trucks than Pittsford. A bypass is needed in Brandon; the number of
trucks will likely increase in the future.
13.
Anyone that lives in an older building along US Route 7 in the villages
can attest to the damage caused by vibration and dust . Bypasses are needed.
14.
With regard to Corridor PE, serious design challenges would be associated
with Furnace and Sugar Hollow Brooks and their associated floodplains: grades
that would require truck climbing lanes, the need for deep ledge cuts, and the
presence of the Proctor Aqueduct.
15.
Is there currently consideration for bypasses for other communities to
the north and south? Could a more
comprehensive plan be considered, rather than a piecemeal approach? Has any consideration been given for linking
a long alternative, such as PBW to US Route 4?
This study has focused on
the villages of Pittsford and Brandon.
If the study is advanced into the EIS process, Federal regulations will
require that a reasonable range of alternatives be considered. Larger-scale projects, as well as rail
travel and freight, Traffic System Management, Traffic Demand Management, and
improvements to other north-south roadways could be considered at that time.
16.
Several in attendance expressed the need to expand the study area to
include more, if not all, of the communities along US Route 7?
Lynn Saunders responded that
perhaps a new Interstate in the westerly part of the State is what is really
needed, but that does not seem likely, given the regulatory and permitting
issues. Bypasses around the Villages
are the most feasible approach.
17.
Consideration should be given to constructing a bypass that would
follow existing abandoned railroad grades, one of which leads directly to
Rutland.
18.
A bypass would only take certain people's frontyard problems and put
them in other people's backyards.
19.
How does this study affect the future salability of property that would
be impacted by one of the conceptual corridors?
A realtor in the audience
responded that all realtors are required to disclose all material facts that
they are aware of with regard to a property.
It should be stressed that this Scoping Study is not intended to set
alignments for construction; its only purpose is to provide the basis for
VTrans's and FHWA's determination of whether to proceed with an EIS.
20.
The Pittsford Fire Chief commented that most accidents are north and south
of the Villages?
Mike Balch responded that
Brandon Village has two very High Accident Locations that are monitored by
VTrans. He also agreed that many
accidents occur north and south of the Villages.
21.
What is a realistic timeframe for construction of a bypass, should the
EIS process prove successful?
Dan Peterson responded that
it may take approximately 20 years to complete the project.
22.
When will the public know whether the study will move ahead?
Dan Peterson responded that
the decision will be made by the next legislative session, approximately one
year from now.
23.
What is the status of the Middlebury Bypass Study?
Richard Baker responded that
studies to Upgrade of the existing road have not yet been completed. Bypasses will not be considered until the
upgrade options have been studied.
24.
Chris Bean asked for a show of hands, to indicate whether the study
should move ahead, into the EIS process.
Of the 33 people from Pittsford in attendance, 9 indicated the study
should move ahead, Of the 36 people in
attendance from Brandon, 21 indicated the study should move ahead.
The meeting
adjourned at 9:45 PM.
CRB:JAS:cww
Attachments
cc: US Rt.
7 Upgrade Steering Committee
Brandon Bypass Steering
Committee
Pittsford Bypass Steering
Committee
PROJECT SCHEDULE
Pittsford and Brandon
Bypass Scoping Studies
·
Scoping
Kickoff Meeting 7/00 11/00
·
Develop
Draft Purpose and Need 8/00 11/00
·
Begin
Steering Committee Meetings 8/00 11/00
·
Begin
Resource Agency (RA) Coordination 9/00 12/00
·
Finalize
Purpose and Need 10/00 1/01
·
Public
Informational Meeting N/A 1/01
·
RA
Meeting (Constraints Maps) 11/00 2/01
·
Steering
Committee Meeting(s) (Alternatives) 1/00 3/01
·
RA
Meeting(s) (Alternatives) 4/01 4/01
·
Steering
Committee Meeting(s) (Alternatives and Issues) 4/01 4/01
·
Public
Informational Meeting (Alternatives) 5/01 5/01
·
Draft
Scoping Report Submitted 8/01
·
Steering
Committee Meeting (Scoping Report) 9/01
·
Public
Informational Meeting 9/01
·
Scoping
Report Published 9/01
·
Public
Meeting/Presentation to TAC and/or RRPC 10/10
PROJECT SCHEDULE
Pittsford-Brandon US
Route 7 Upgrades
Approximate Timetable - to
be expedited if possible
Conceptual Plans
submitted to VTrans June,
2001
Categorical
Exclusion Documentation Fall
2001
502 Public Hearing Fall
2001
Preliminary Plans Summer
2002
Property Owner
Meetings Winter
2002
Semi-Final plans Spring
2003
Right-of-Way
Process Spring
2003 - Fall 2004
Necessity Hearing Fall
2005
Compensation
Hearing Spring
2006
Final Plans Spring
2006
Advertise for
Construction Summer
2006
Revised 05/2001