M E M O R A N D U M
TO: File
FROM: Jason A. Stone
DATE: April 23, 2001
RE: VTrans
Brandon Scoping Study
NH 019-3(49)SC
CLD Ref No. 00-0216
Subject: Brandon
Bypass Steering Committee Meeting
Location: Brandon
Masonic Hall
attendees: In
addition to those listed below, nine members of the public attended the
meeting.
Peg
Flory Pittsford
Selectboard PBSC, BBSC
Mike
Balch Brandon
Town Manager BBSC
Richard Baker Brandon Citizen BBSC
Dolores Furnari Brandon Citizen BBSC
Dan Peterson VTrans Project Manager PBSC, BBSC
Bob Woods State Representative
Greg Riley VTrans, Regional Planning
Chris Bean CLD Engineers Project Manager PBSC, BBSC
Jason Stone CLD Engineers Environmental Specialist
UNABLE TO ATTEND: Lynn Saunders - BBSC, PBSC
BBSC Brandon Bypass Steering Committee Member
PBSC Pittsford Bypass Steering Committee Member
Meeting Notes
1. Introductions/Purpose of Meeting
Chris Bean made general introductions of those present. Chris then explained that the purpose of the meeting was to discuss and/or receive input on the following issues:
·
The
April 11, 2001, Corps Resource Agency Coordination Meeting
·
Revisions
to the Environmental Constraints Mapping
·
Revisions
to the Conceptual Corridors and Associated Changes in Structures Impacts
·
Consolidated
Project Purpose and Need Statement
·
Determine
the Dates and Locations for Upcoming Meetings
2. April 11, 2001, Corps
Resource Agency Coordination Meeting Update
The purpose of this meeting was to provide the Resource Agencies an opportunity to provide VTrans and FHWA input, regarding the prudence of taking the Bypass Scoping Study process ahead and into the formal Environmental Impact Statement (EIS) process. Jason Stone summarized the discussions that took place. He explained that CLD provided the Resource Agencies with constraints mapping, impact matrices and acetate overlays depicting the conceptual corridors, prior to the meeting. He added that the Resource Agencies were asked to review the information, and to: provide input regarding the accuracy of the constraints mapping (macro-level); suggest possible revisions to the conceptual corridors; and to comment, from their respective agency's perspective, as to whether the level of resource impacts associated with the conceptual corridors would lead to the conclusion that an EIS would not be a prudent investment.
Resource Agency Comments From the April 11, 2001 Meeting
·
Wetlands: Peter
Keibel (VTANR) provided information relative to Class I and II wetlands around
Brandon Village indicating the GIS National Wetlands Inventory data layer CLD
used was not complete. Peter indicated
he would check with the VCGI staff and try to determine whether other
inaccuracies exist. Others with
familiarity with the project area suggested that much of the floodplain area
west of US Route 7 is very likely to be Class II wetland. CLD has incorporated this information into
the constraints mapping and updated the impact matrix accordingly.
·
Ground-Truthing
Constraints:
John Lepore (VTrans Environment) asked to what extent the constraints
had been ground-truthed. Dan Peterson
responded that there is neither time nor budget in this scoping study for such
efforts. Dan added that for the purpose
of this scoping study, which is only to determine whether more detailed studies
should be conducted, information of planning-level accuracy is sufficient.
·
Overall
Permitability:
Peter Keibel qualified his next comment and stated that he would not
speak for his agency, but in his personal opinion, the long bypasses would not
be likely to withstand the regulatory and permitting processes. He felt that the short bypasses could
conceivably succeed.
·
USEPA
Request for Additional Information: Beth Alafat (USEPA) stated that she had not
been made aware of conceptual corridors prior to the meeting. She added that her agency has not received
sufficient information, and it would be inappropriate to provide comments. She stated she would like to see traffic
information to support the projects' stated purpose and need, and that other
measures (rail, Traffic Demand Management (TDM), Traffic Systems Management
(TSM), etc.) must be evaluated before her agency will even begin to consider a
bypass as a viable option. She
reiterated her comments from the February 7, 2001 Resource Agency meeting that
upgrade of the existing facility should be the first option. Chris Bean, Mike Balch, John Lepore and
others responded that projects to upgrade the existing facility have already
been studied, and are planned for construction in the next several years. A conclusion of the Upgrade Studies is that
within the villages, there are sufficient natural and cultural resource
constraints to preclude the widening necessary to handle the projected future
year traffic volumes. Bypasses are
therefore necessary to provide the highway capacity required for the projected
volumes. Of course, if the project
moves forward into the EIS phase, detailed analyses of alternatives including
TDM and TSM options, will be considered to ensure that bypasses are
warranted. The EPA has been provided
with a copy of the Scoping Report prepared for the Upgrade Projects.
·
USACOE
Project Manager:
Mike Adams indicated that he would serve as the ACOE Project Manager for
these projects. He agreed with Peter
Keibel, that the long bypass alternatives would not be likely to succeed.
·
VTANR
- Fish and Wildlife Division (Via e-mail): Subsequent to the April 11, 2001, Resource
Agency meeting, VTrans received input from Forrest Hammond of the VTANR Fish
and Wildlife Division, essentially echoing the sentiments expressed by the
other Agencies, that the shorter corridor alternatives appear to be more
favorable than do the long alternatives around both villages.
·
Consolidated
Purpose and Need Statement: The consolidated Purpose and Need Statement
was provided to the Agencies, for their information.
·
Summary: Chris Bean noted that the Agencies did not
give a clear indication that the study should move ahead, nor did they indicate
that it should not. Chris and Dan
Peterson both noted that the Bypass Scoping Study falls outside the normal
coordination process, and therefore the agencies' unfamiliarity with this
process may in part explain their reluctance to comment. Chris explained that the agency
representatives may be thinking that commenting favorably would jeopardize
their ability to be objective in the future.
Mike Balch added that more consistent attendance and representation by
the Agencies would be beneficial to the process.
3. Revisions to the Environmental
Constraints Mapping
As indicated above, the wetlands data layer has been updated based on information provided by VTANR.
4. Revisions to the Conceptual Corridors
and Associated Reduction in Structures Impacts
At the last Steering Committee Meeting, CLD committed to take a closer look at the Structures Impacts, as it was felt that the impacts were overestimated, and not a true indication of actual displacements. This analysis was done by superimposing the conceptual corridors over the aerial photograph data layer, and then determining whether affected structures were actually residences or some other type of building. A general reduction in impacted structures (residences) resulted.
The conceptual corridors were originally drawn onto the constraints map at a large scale. When conducting the above-described analysis, it was apparent that modifying the conceptual corridors could significantly reduce impacts to structures, especially where they match into US Route 7, and intersect other roadways. The revised conceptual corridors were presented to the Steering Committee and were generally accepted. The revised corridors were presented in an alignment format, with the bypasses intersecting existing US Route 7 at 90o T-intersections. When the revised corridors are developed, making the bypasses or the existing US Route 7 the through route will be evaluated. CLD will make that change, and revise the impact matrix to reflect the modified corridors.
5. Next Steps
A Joint
Public Informational Meeting has been tentatively scheduled for Monday, May 21, 2001, at 7:30 PM, at Otter
Valley Union High School. The meeting
date and location will be confirmed as soon as possible. The revised conceptual corridors and impact
matrix, as well as preliminary Bypass Scoping Study conclusions, will be
presented to the public.
The next Brandon Bypass Steering Committee Meeting has been tentatively scheduled for Monday, July 23, 2001. The location is yet to be determined. The meeting will start at 5 PM and run no later than 6:30 PM, to allow Steering Committee Members to attend the Selectmen's Meeting, which begins at 7:00 PM. A presentation will be made to the Selectmen, to update them on the status of the project.
It is anticipated that the next Pittsford Bypass Steering Committee Meeting will be scheduled to coincide with the date of the next Pittsford Selectmen's meeting. The meeting would be scheduled in a similar manner as the Brandon Meeting, to allow Steering Committee Members to attend both meetings. A presentation will be made to the Selectmen, to update them on the status of the project.
Another Joint Public Informational Meeting will be held in August, 2001, to present the final report documenting the findings of the Bypass Scoping Studies.
CLD anticipates completion of the Final Bypass Scoping Study Report in September, 2001.
JAS:cww
|
cc: Lynn Saunders |
Brandon |
Chris
Slesar |
VTrans |
|
Peg Flory |
Pittsford |
John
Narowski |
VTrans |
|
Richard Baker |
Brandon |
Mark
Blucher |
RRPC |
|
Jim O’Gorman |
Pittsford |
Mark
Germanowski |
RRPC |
|
Mike Balch |
Brandon |
Susie
Leonard |
RRPC |
|
Hank Pelkey |
Pittsford |
Judith
Kmileck |
RRPC |
|
C. Baird Morgan |
Pittsford |
Kathleen
Ryan |
Landscape
Architect |
|
Dolores C. Furnari |
Brandon |
Gary
A. Klinefelter |
VSE |
|
Dan Peterson |
VTrans |
Virginia
Russell |
State
Transportation Board |
|
Alan Neveau |
VTrans |
Jon
Satz |
Store
Owner, Brandon |
|
Scott Newman |
VTrans |
Sen.
Gerry Gossens |
State
Senator |
|
Duncan Wilkie |
VTrans |
Roy
Newton |
Brandon-Pittsford Reporter |
|
Chris Borstel |
Louis
Berger Group |
Ed
Barna |
Rutland Herald |
|
Greg Riley |
VTrans |
Frank
Farnsworth |
Otter Valley Press |
|
Dennis Benjamin |
VTrans |
Harry
McKinley |
Pittsford |