M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: March 8, 2001
RE: VTrans
Pittsford and Brandon
Bypass Scoping Studies
NH 019-3(49)SC
CLD Reference No. 00-0216
Subject: Brandon Bypass Steering Committee Meeting
Location: Lothrop
Elementary School Gymnasium
attendees: In
addition to those listed below, six members of the Hill and Hollow Alliance
attended the meeting. Mike Balch (BBSC)
was unable to attend.
Lynn
Saunders Brandon Selectboard BBSC,
PBSC
Richard
Baker Brandon
Citizen BBSC
Peg Flory Pittsford Selectboard BBSC, PBSC
Dolores Furnari Brandon Chamber of Commerce BBSC
James O'Gorman Town of
Pittsford PBSC
Dan Peterson VTrans Project Manager BBSC, PBSC
Chris Bean CLD Engineers Project Manager BBSC, PBSC
Jason Stone CLD Engineers Environmental Specialist
Greg Riley VTrans, Regional Planning
BBSC Brandon Bypass Steering Committee Member
PBSC Pittsford Bypass Steering Committee Member
Meeting Notes
1. Introductions/Purpose of Meeting
Chris Bean made general introductions of those present. Chris then explained that the purpose of the meeting was to discuss and/or receive input on the following issues:
· February 7, 2001, Corps'
Resource Agency Coordination Meeting Update
· Consolidated Project Purpose
and Need Statement
· Consensus regarding access
to the bypass highway
· Conceptual Corridors
developed to date
· Conceptual Corridors Impact
Matrix
2. VTrans Project Manager
Dan Peterson indicated that there has been no change in the project manager status. He will likely continue as VTrans Project Manager for the duration of the bypass studies.
3. February 7, 2001, Corps' Resource Agency
Coordination Meeting
Chris summarized the input received from the
Natural Resource agencies. He explained
that initially, the agencies (VT ANR, in particular) were concerned that the
project was moving ahead too quickly, and without sufficient Agency and/or
Public oversight, review, and input.
This concern was allayed once the purpose of the Scoping Studies, which
is to assist FHWA in determining whether more detailed design and environmental
studies should be pursued, was better explained. Once it was made clear that the Scoping Studies will not set true
alignments, the Agencies were more comfortable with the Scoping Studies
proceeding.
Lynn Saunders asked whether VT ANR should be
added to the Steering Committee distribution lists, to keep that agency
informed. It was decided to add VT ANR
to the lists.
4. Consolidated Project Purpose and Need
Statement
A consolidated version of the Purpose and Need
Statements has been prepared to assist the Corps in the preparation of their
Project Purpose and Need Statement, should the project(s) move ahead with more
detailed (EIS level) study. Refer to
the attached consolidated Purpose and Need Statement. Richard Baker noted that there is no mention of the effect of a
Bypass on local traffic and access issues.
The consolidated Purpose and Need Statement will be revised in this
regard.
5. Environmental Constraints Maps
Chris Bean noted that environmental constraints
maps have been provided to both Towns and Steering Committees, as well as the
Natural Resource Agencies. Chris asked
if anyone present had any comments on the constraints as mapped. Dave Martin and Chris Eddy (both of the Hill
and Hollow Alliance) stated that the Bear Habitat and Deer Wintering Area
constraints appear to be underrepresented based on their personal
experiences. They asked how recent was
the information used to create the mapping.
It was explained that although the exact dates were not known at the
time of the meeting, CLD used the most recent information available. It is believed that the information used is
of sufficient accuracy for the purposes of the Scoping Studies.
6. Hill and Hollow Alliance
Dave Martin of the Hill and Hollow Alliance
asked to read a short statement into the meeting record (see attachment). Essentially the Hill and Hollow Alliance
supports the US Route 7 Upgrade Projects, as well as the continued study of
limited Bypasses. The group is opposed
to major relocations of US Route 7, especially to the east.
7. Conceptual
Corridors
Chris began the
discussion of the conceptual bypass corridors and explained that they are a
first attempt to find locations for bypasses that appear to avoid and minimize
impacts to the mapped resource constraints.
CLD has been asked to consider short bypasses, east and west of US Route
7, around the Pittsford and Brandon Village areas only, as well as two long
bypasses, one east and one west of US Route 7, around both villages. Therefore six conceptual corridors were
presented on an acetate overlay.
Chris described the naming convention used for
the conceptual corridors. For the short
corridors, the first letter denotes the Town, the second letter denotes whether
the corridor lies east or west of US Route 7, and the following numbers denote
variations of corridors. For example,
Corridor BE1 is a short corridor around the east side of Brandon Village. The long alternatives are similarly
named. The first two letters refer to
the Towns and the following letter denotes its location, either east or west of
US Route7. Peg Flory asked the lengths
of the short Brandon corridors. BE1 is
approximately 5 miles long and BW1 is approximately 2.6 miles long.
Chris explained that the corridors are 150 feet
in width. This width was chosen as a
conservative approximation of the impact footprint of a two-lane highway with
shoulders and potentially with truck climbing lanes, if warranted. It was felt that using an approximation of
the impact footprint, versus a given right-of-way width to be acquired, would
provide a more accurate estimation of impacts.
Without a climbing lane the highway pavement would be 40 feet wide (two
12-foot lanes, 8-foot shoulders). With
a truck lane the pavement would be 44 feet wide (three 12-foot lanes, 4-foot
shoulders). Roadway cut and fill slopes
and drainage ditches and structures would account for the remainder of the
impact footprint, though the exact extent of impacts will not be determined
during this study. For this study, it
is only necessary to obtain a reasonable estimation of impacts for the various
conceptual corridors, to see whether any locations appear to be worthy of
further consideration, given the current regulatory and permitting
processes. It should be noted that an
additional 50 feet was added to each side of the conceptual corridors for
calculating impacts to resources that are recorded as "point data,"
to account for "near misses."
For example, houses and other structures are recorded in the ArcView
data layers simply as points. If a
point were to be located just outside the 150-foot corridor, it would not be
counted as an impact, though in reality the structure associated with the point
would, in all likelihood, be impacted.
This approach results in an overall corridor width of 250 feet with
regard to "point data."
Chris asked whether there was consensus among
the Steering Committee Members regarding access to the Bypass. Chris explained that with a limited access
facility, access would only be provided at intersections with VT State
Highways. No connection to local Town
roads would be provided. Connections to
State Highways would logically be via grade-separated interchanges, or possibly
at-grade intersections. Design of such
interchanges will not be performed as part of this study. It was unanimously agreed among the Steering
Committee Members that for the purposes of this study, the bypass facility
should be considered as a limited access facility. Chris mentioned that a limited access facility might meet with
less resistance from the Natural Resource Agencies, as the opportunities for
secondary impacts are limited. Lynn
Saunders noted that development rights could be acquired along the State
Highways, within a given distance of the Bypass, to further limit secondary
impacts.
8. Impact Matrix
Jason Stone described the impact matrix prepared
for the six conceptual corridors. The
constraints listed are the same as those depicted on the constraints maps (see
attachment). Generally, the long
conceptual corridors impact resources to a greater degree than do the shorter
corridors, with the possible exception of impacts to structures. Of the two long corridors, it appears that
PBW would result in greater impacts to resource constraints of high
sensitivity, such as wetlands, surface waters and floodplains. This alternative would, however, result in
lesser impacts to prime farmland soils (two acres versus four acres with PBE),
and possibly lesser impacts to historic structures. It should be noted that impacts to structures currently include
all buildings. For instance, if a
residence, a separate garage, and another outbuilding on one property were to
be impacted, the impacted structures would be counted as three. Therefore, this approach has the potential
to inflate the totals for actual impacts to residences. Impacts to structures will be looked at more
closely and refined to provide more accurate totals.
With regard to the short corridors around
Brandon Village, BE1 appears to impact resources to a greater degree than does
BW1. BW1 does impact more historic
structures (four versus one with BE1), and requires two railroad crossings
(versus none with BE1). As stated
above, impacts to structures, including historic structures, will be looked at
more closely.
9. Conceptual Corridor Revisions
Chris asked whether the Steering Committee
Members had any suggested revisions to the conceptual corridors. It was suggested that the northerly terminus
of corridor BW1 be looked at more closely to determine whether a town-owned
recreational field would be impacted.
Richard Baker thought that Land and Water Conservation Funds might have
been used in the area, on a property known as Estherbrook (sp?) Field. It was suggested that the corridor could
possibly be shifted to impact a house that is currently for sale, to avoid the
field if necessary. Also with regard to
corridor BW1, a house depicted as historic may, in fact, no longer have
integrity, due to extensive recent revisions, and the location of the Waste
Water Treatment Plant was brought up.
These issues will be looked into, and the constraints maps will be
revised as appropriate.
10. Next Meetings
The next Bypass
Steering Committee Meetings have been scheduled for Monday, April 23, 2001, at the Brandon Masonic
Hall, located at the intersection of Country Club Road and Park Street, in
Brandon. The Brandon Bypass Steering
Committee Meeting will start at 4:00 PM and run until 5:30 PM, and the Pittsford
Bypass Steering Committee Meeting will begin at 6:00 PM and run until 7:30 PM.
The project will be
presented at the next Corps Natural
Resource Agency Meeting, scheduled for Wednesday April 11, 2001, at the VTrans Headquarters in the National Life Building,
Montpelier, VT. The time of the
presentation is yet to be determined.
CRB:cww
Attachments
|
cc: Lynn Saunders |
Brandon |
Mark
Blucher |
RRPC |
|
Peg Flory |
Pittsford |
Mark
Germanowski |
RRPC |
|
Richard Baker |
Brandon |
Susie
Leonard |
RRPC |
|
Jim O’Gorman |
Pittsford |
Judith
Kmileck |
RRPC |
|
Mike Balch |
Brandon |
Kathleen
Ryan |
Landscape
Architect |
|
Hank Pelkey |
Pittsford |
Gary
A. Klinefelter |
VSE |
|
Dan Peterson |
VTrans |
Virginia
Russell |
State
Transportation Board |
|
Alan Neveau |
VTrans |
Jon
Satz |
Store
Owner, Brandon |
|
Scott Newman |
VTrans |
Sen.
Gerry Gossens |
State
Senator |
|
Duncan Wilkie |
VTrans |
Roy
Newton |
Brandon-Pittsford Reporter |
|
Chris Borstel |
Louis
Berger Group |
Ed
Barna |
Rutland Herald |
|
Greg Riley |
VTrans |
Frank
Farnsworth |
Otter Valley Press |
|
Dennis Benjamin |
VTrans |
Harry
McKinley |
Pittsford |
|
John Narowski |
VTrans |
|
|