M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: February 23, 2001
RE: VTrans
Pittsford-Brandon
US Route 7 Upgrade CLD Ref. No. 00-0219
Pittsford Bypass CLD Ref. No. 00-0215
Brandon Bypass CLD Ref. No. 00-0216
SUBJECT: Meeting
with Senate Transportation Committee
LOCATION: Vermont State House
ATTENDEES: Senator Dick Mazza (Chair) Representing Grand Isle
Senator Tom Bahre Representing Addison
Senator John Crowley Representing Rutland
Senator Peter Shumlin Representing Windham
Senator Rob Ibe Representing Caledonia
Senator Cheryl Rivers Representing Windsor
Sherri Burch Senate Transportation
Committee
Rep. Peg Flory Pittsford Steering
Committee Member
Lynn Saunders Brandon Steering
Committee Member
Mike Balch Brandon Town
Manager, Steering Committee Member
Dan Peterson VTrans Project Manager
Chris Bean CLD
Purpose of Meeting: To update the Committee on the status of the
Pittsford and Brandon US Route 7 projects.
1. Introductions
Dan introduced the Town officials
and Members of the Steering Committee.
Representative Flory, Lynn Saunders, and Mike Balch noted that the
Steering Committee process has been very effective on these projects. Its success has resulted in an atmosphere
which addresses issues as they develop in a constructive fashion so that
resolution can be developed and progress can continue on the projects. They also thanked the Senate Transportation
Committee (STC) for their support and pledged to continue working towards the
ultimate goal of completing work on the upgrade projects and the bypass
studies.
2. Major
Accomplishments in 2000 (Presented by Dan Peterson)
A. Scoping Report: Since the last meeting with the STC, the
Scoping Report detailing the six proposed upgrade projects along the existing
11.5 mile corridor was completed and approved in May 2000. A handout depicting the individual project
segments was distributed (copy attached).
B. Conceptual Plans: CLD began development of Conceptual Plans in August
2000. Conceptual Plans for Project
Segments 4 and 6 have been submitted and are currently under review. Conceptual Plans for the remaining segments
will be submitted within a couple months.
C. Archeological Issues: In the summer of 2000, an extensive
archeological investigation was completed along the entire corridor. The field work involved 1,155 shovel tests,
35 excavations 1 m x 1 m in size, and 11 hand-dug trenches 2-3’ wide x 120’
long. The conclusions show that there
are no issues of concern within the proposed work limits of segments 1, 2, 3,
and 6. Within segment 5, there is an
area of concern in the vicinity of Jones Mill Pond. Within segment 4, there are concerns mostly in the vicinity of
Fort Vengeance. Within this potential
historic area, remains of the fort have not been found; however, remains have
been found of the Hendee Tavern, which was associated with the fort. Investigation in this area will be
continuing and alternative alignments are currently being studied to avoid
and/or minimize impacts. Should impacts
be unavoidable, an expected data recovery operation will most likely be
required. Louis Berger and Associates
are completing the archeological investigation. Their fee for this work is approximately $340,000, of which
$210,000 has been spent to date.
D. Historical Assessment: CLD has been working with Scott Newman,
VTrans Historic Preservation Coordinator.
Scott has been coordinating with the Vermont Division of Historic
Preservation in connection with several anticipated impacts within either
historic districts or potentially historic properties along the various project
segments. One particular location is
the Bloodworth House located on the west side of US 7 about ¼ mile south of the
intersection with VT 3. An early
acquisition of this potentially historic structure is being considered. In addition, the design of improvements
within Pittsford Village in the area of the sharp curve at the northerly
intersection with Arch Street has been coordinated with the library such that library
officials are satisfied with the concept.
Within Brandon, the Brandon green is proposed to be reconfigured to
address a high accident location at the “sharp curve.” This work will necessitate reconfiguration
of the Town green and impact along the frontages of some properties in this
area. The proposed configuration will
result in a safer roadway, as well as an enhanced Brandon green, in that it
will be larger and contiguous with the existing monument at the intersection
with VT 73, just south of the green.
3. Budget
Initial Project Scoping
(Rist-Frost-Shumway) $ 225,000 (villages
only, initial phase only)
CLD Scoping 530,000 (villages and corridor section)
CLD Conceptual Design 630,000 (11.5 miles)
CLD Permitting 220,000 (11.5 miles)
Louis Berger Associates (LBA)
Archeology 336,500 (11.5 miles)
VTrans 100,000
Total $2,041,500
Spent
to Date $1,300,000
Balance $ 700,000
Budgeted
for FY 2002 $ 450,000
The question was then asked whether
lack of funding is holding up progress on the project. Dan indicated no, it is not holding it up at
this time.
4. Upgrade
Project Schedule
At this time, the schedule for each
of the projects is being estimated along the following time line:
·
Complete Conceptual Plan Spring 2001
·
Complete Environmental Documentation Summer 2001
(Categorical
Exclusion)
·
502 Public Hearing Summer 2001
·
Preliminary Plans Winter 2001/2002
·
Property Owner Meetings Summer 2002
·
Semi-Final Plans Fall
2002
·
Right-of-Way Process Fall 2002-Spring 2003
·
Final Plans Spring
2005
·
Advertise for Construction Spring-Summer 2005
It
was noted that both the Brandon and Pittsford Village projects may be processed
as municipally managed projects. This
may allow for a more expedited project schedule. (Also see #5.)
5. Right-of-Way
Dan explained that although the
Agency believes there is a historic 5-rod (82.5-foot) wide right-of-way
throughout most of the project, due to lack of historical evidence, the
decision has been made to claim the statutory 3-rod (49-foot) right-of-way. The exception will be within the Town of
Brandon where a wider right-of-way will be claimed due to the existence of
historical evidence supporting same.
This may allow the project within Brandon, which is expected to be
municipally managed, to proceed on a faster completion schedule than the other
projects since less taking of right-of-way will be required. All right-of-way takes for this project are
proposed to be in fee as opposed to easements.
Land required to be taken beyond the existing right-of-way limits will
be taken at current market value.
6. Pittsford
and Brandon Bypass Scoping Studies
A. Purpose of Bypass Scoping Studies: Chris explained that the purpose of the
scoping studies is to determine whether there is a justification to begin a
costly environmental impact statement process.
The scoping studies will identify sensitive natural resource constraints
and determine the potential social and economic impacts of a few proposed
bypass corridors. The studies will then
include a summary of impacts associated with the alternatives and a final
determination and recommendation will then be given as to the whether
completion of a thorough Environmental Impact Statement (EIS) is prudent. The Federal Highway Administration (FHWA) is
especially interested in the study outcome, since the FHWA would provide the
majority of funds to pay for a potential EIS.
B. Purpose and Need: Chris stated that the major purpose is to separate the
current traffic usage of US 7 within the villages, which includes a significant
number of through vehicles consistent with the designation of this highway as a
National Highway System route, from local traffic and local traffic needs,
including parking, driveways to residences and businesses, and numerous
intersections with town roads. The need
for a bypass has been the subject of several public meetings in the communities
where residents have expressed concerns about the inability to gain access to
the highway due to heavy volumes of both passenger cars and trucks, noise,
vibration, dust, and pedestrian safety.
C. Environmental Constraints Mapping: Chris reviewed a graphic which showed
significant historical, water resources, and endangered species in the study
area. He further explained that
additional constraints such as farmland, deer and bear habitat, conserved
lands, and locations of endangered species have been mapped.
D. Bypass Traffic Considerations: Chris presented a graphic showing the
anticipated traffic volumes with and without a bypass in both Pittsford and
Brandon for the years 2000 and 2025.
The graphic was generated based on information obtained from an October
2000 Origin-Destination Study. The
graphic showed that a bypass in each community would reduce the projected
future average daily traffic from 14,100 to 3,700 in Pittsford and from 17,000
to 6,600 in Brandon.
E. Bypass Scoping Project Schedule: The Bypass Scoping Report is scheduled
to be completed in summer 2001.
F. Budgeted Funds
Pittsford:
CLD $160,000
LBA $ 10,000
VTrans $ 30,000
` Total $200,000 (programmed October 2000)
Brandon:
CLD $160,000
LBA $ 10,000
VTrans $ 40,000
Total $200,000 (programmed October 2000)
Dan indicated that the
work completed under the development and evaluation budget for scoping in FY
2001 is $2.7 million. The STC requested
and Dan agreed to get back to them with the amount of FY 2001 funds proposed
for the Pittsford and Brandon Bypass Scoping Projects. Dan further indicated that there is no money
in the State FY 2002 budget for Pittsford and Brandon Bypass projects.
7. Senate
Transportation Committee Input
Throughout the presentation,
Committee members asked general questions about the projects. Responses were given to each question. The STC endorsed the project and requested
that they continue to be kept informed of the project status, especially if any
barriers are encountered in the design process.
CRB:cww
Attachments
|
cc: Sherri Burch Lynn Saunders |
Dan
Peterson |
Mark
Blucher |
Roy
Newton |
|
Michael Balch |
Greg
Riley |
Mark
Germanowski |
Frank
Farnsworth |
|
Richard Baker |
Dennis
Benjamin |
Susie
Leonard |
Virginia
Russell |
|
Dolores Furnari |
Duncan
Wilkie |
Judith
Kmileck |
Sen.
Gerry Gossens |
|
Peg Flory |
John
Narowski |
Chris
Borstel |
Harry
McKinlay |
|
James O’Gorman |
Scott
Newman |
Gary
Klinefelter |
|
|
Hank Pelkey |
Alan
Neveau |
Kathleen
Ryan |