M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: February 12, 2001
RE: VTrans
Pittsford-Brandon NH
019-3(49)SC
CLD Reference No.
00-0219, 00-0248
SUBJECT: US
Route 7 Upgrade Steering Committee Meeting, 02/12/01
LOCATION: Brandon Fire Station
ATTENDEES: *Peg Flory Town of Pittsford
*James
O’Gorman Town of Pittsford
*Hank
Pelkey Town of
Pittsford
*Dan
Peterson VTrans, Project Manager
*Greg
Riley VTrans, Planning
Coordinator
Roy M. Newton Brandon-Pittsford
Reporter
Mark Germanowski Rutland Regional Planning Commission
Bob Wood Representative,
District R-2
Jason Stone CLD
*Chris
Bean CLD
*Route
7 Upgrade Steering Committee Member
MEETING NOTES
1. Conceptual
Plans Development
·
Schedule
Chris Bean explained
that conceptual plans for Project Segment 4 have been submitted. Plans for Project Segment 6 were provided to
VTrans and the Towns on this date. CLD
is requesting that comments on both Project Segments be provided by February
23, 2001, so revisions can be made in advance of the Comments Review Meeting,
scheduled for March 7, 2001 (see below).
Chris indicated that the plans for the remaining segments are
forthcoming. Submittals for Project
Segments 1 and 2 are targeted for mid- to late February. Richard Baker asked whether the plans for
Segment 6 included a traffic signal at the intersection of US Route 7 with
Carver and Union Streets. Chris
responded that a signal is included, though it has not been fully designed at
this point.
Dan Peterson suggested
that before additional submittals are made (prior to the March 7 Comments
Review Meeting), it may be beneficial to complete the reviews of Project
Segments 4 and 6. Dan felt that many
comments on these submittals would likely be applicable to subsequent
submittals as well, and a savings in review time would be realized. It was agreed to delay the submittals for
Segments 1 and 2.
Peg Flory asked if any
Division of VTANR should be provided with conceptual plans. Dan Peterson said he would check to see if
VTANR staff would like to review plans at this stage of the project.
Chris mentioned that
construction cost estimates are included in the submittals. Costs are higher than originally
anticipated. One of the causes for this
is the shift from rubblization of the concrete roadbed to removal of the
concrete with full-depth reconstruction.
Other increases are due to increases in unit item costs, such as the per
ton price of bituminous pavement. Chris
mentioned that the improvements made by these projects would be in place for a
long time before the project area is improved again. Chris noted that Dan Peterson has gone on record as stating that
even if costs are somewhat higher than originally anticipated, funds should be
spent to ensure the projects are "done right," and long-lasting
improvements are made.
·
Montpelier
Comment Review Meeting
Comments on the
Conceptual Plans will be reviewed on March 7, 2001, at VTrans - National Life
Building in Montpelier, VT. The meeting
is scheduled to begin at 10:00 AM.
Members of the Steering Committees are welcome. It was noted, however, that the discussions
are generally detail-oriented and focus on technical issues.
Roy Newton asked when
the next opportunity for the general public to see the plans would be. As there is not another Public Informational
Meeting scheduled, the Public Hearing will be the next formal opportunity for
public input. It was noted that plans
will be available for review at each Town Office and the public may provide
comments through the Steering Committee at any time.
2, Mailbox
Locations in Pittsford Village
Chris summarized the
issue as follows. Presently mailboxes
in Pittsford Village are located at the edge of the pavement. Curbing is either nonexistent or has become
obscured/buried, and does not represent a barrier to mail delivery
vehicles. In most locations there is at
least ten feet of space between the boxes and the travelway. Adequate room exists for the mail delivery
vehicle to pull over, out of the travelway, and make deliveries without
impeding traffic flow. With the
proposed typical in place, there will not be adequate room for the delivery
vehicle to pull over, and allow vehicles to pass, without crossing over into
the opposing travel lane. This
situation is a safety concern for the public, as well as the mail delivery
personnel.
Peg Flory stated that
it is up to the Town of Pittsford to push for door-to-door mail delivery. She explained that it is hard to know what
information the Postal Service requires to justify a change in modes of
delivery, as it does not appear that guidelines exist. Peg indicated that perhaps the time has come
to involve others in VT State Government in the Town's dealings with the Postal
Service. Dan Peterson added that the
Postal Service needs to be made aware of the safety issues involved. Richard Baker noted that in addition to the
mail delivery vehicles, the owners of the mailboxes would also impede traffic
flow when getting their mail.
Mailbox clusters were
discussed as an option-to-door to door delivery. Peg Flory mentioned that based on input she has received,
proposing mailbox clusters would result in increased opposition to the project.
Door-to-door delivery, limited to properties fronting US Route 7 only, was
suggested. Chris suggested that
locating mailboxes at the back edge of the sidewalks or the right-of-way may be
an option. This would require delivery
vehicles to make regular stops where space allows and then deliver mail to the
boxes on foot. This would require less
time than door-to-door delivery, as it would not require walking all the way to
the doors of residences.
Mike Balch stated that
VTrans is not required to allow mailboxes within the State's right-of-way. He asked Dan whether VTrans would be willing
to require their removal, and force door-to-door delivery. Dan responded that he was not aware of any
instance where this has occurred, although it may have at some location. He added that he would rather the issue be
worked out between the Town of Pittsford and the Postal Service, and again
cited the safety issue as an incentive for the Postal Service to adopt
door-to-door delivery.
3. Archeology
- Matrix of Design Alternatives
CLD is developing
design alternatives to avoid and/or minimize impacts to the Fort Vengeance
Monument Site, which VTrans has determined to be National Register-eligible
(see attached matrix). VTrans's
archeological consultant (Louis Berger) will provide information relative to
the depth of the archeological deposits in the area to assist in determining
the level of impacts associated with the various alternatives.
Chris presented a
roadway profile graphic and roadway plan of the Monument area, including the
"Pomainville sag," and explained that the proposed northbound truck
climbing lane contributes to impacts at the Monument Site. Some of the alternatives that would lessen
impacts to the Monument Site involve shortening the climbing lane by beginning
it approximately 0.3 mile further to the north. The climbing lane would then be about 0.5 miles in length. Chris explained the analysis that defines
where the climbing lane is warranted, and noted it is based in part on the
speed that trucks are traveling as they enter the proposed climbing lane. The analysis clearly shows that the area
where the lane could be shortened is where the climbing lane is needed most,
i.e., trucks would reach their slowest speed prior to the shortened lane, and
would be accelerating as they reached the lane. The Steering Committee favored leaving the climbing lane as it is
currently proposed, recognizing that it is the only climbing lane in the
northbound direction, in the project area.
The proposed gravel
parking area at the Monument Site was discussed. Chris explained that unless VT DHP changes its philosophy on the
placement of fill within the Site's National Register boundary, constructing
the parking lot would require additional archeological resource recovery work,
and add time and money costs to the project.
It was the Steering Committee's preference to eliminate the parking lot
from the project. It was noted that the
driveway to the parking lot was within the proposed climbing lane. Northbound motorists would make the left
turn maneuver into the drive from the high-speed lane. This is a safety concern, especially if
motorists had to wait for a gap in southbound traffic before turning. Chris noted that the turning volumes would
be very low, but the driveway location is certainly less than ideal.
4. Other
Issues
·
Project
Segment 3 - Alignment Issue, Broken-Back Curve
Chris explained that a
"broken-back curve" (two horizontal curves separated by a very short
tangent section) exists in the existing alignment, between roadway design
Stations 10+460 and 10+800. Chris explained
the standard treatment would be to replace the two curves with one sweeping
curve to eliminate the tangent section.
Doing this would impact more land along the inside of the curve, but
would also reduce impacts on an historic property located at roadway design
Station 10+680, left. The Steering
Committee favored eliminating the tangent section. CLD will implement this alignment revision.
·
Act
250 Coordination
Peg Flory informed
VTrans, CLD, and the Steering Committee that a bill before the Legislature
would exempt roadway projects that did not extend beyond 50 feet from the
existing centerline, from the Act 250 review process. It was not clear how the 50-foot distance should be
measured. If the measurement were taken
from the existing to the proposed centerline, the overall US Route 7
Improvements could probably be designed to meet the exemption
requirements. Peg will look into how
the 50-foot distance is measured.
5. Next
Meeting
·
US
7 Upgrade Steering Committee
Monday, March 19, 2001, from 4:00 to 7:00 PM, at
the Pittsford Municipal Building.
CRB:cww
Attachment
|
cc: Lynn Saunders |
Dan
Peterson |
Mark
Blucher |
Roy
Newton |
|
Michael Balch |
Greg
Riley |
Mark
Germanowski |
Frank
Farnsworth |
|
Richard Baker |
Dennis
Benjamin |
Susie
Leonard |
Virginia
Russell |
|
Dolores Furnari |
Duncan
Wilkie |
Judith
Kmileck |
Sen.
Gerry Gossens |
|
Peg Flory |
John
Narowski |
Chris
Borstel |
Harry
McKinlay |
|
James O’Gorman |
Scott
Newman |
Gary
Klinefelter |
|
|
Hank Pelkey |
Alan
Neveau |
Kathleen
Ryan |
|
|
C. Baird Morgan |
Paul
Tober |
Ed
Barna |
|