M E M O R A N D U M
TO: File
FROM: Christopher R. Bean, P.E.
DATE: January 29, 2001
RE: VTrans
Brandon Bypass Scoping
Studies
NH 019-3(49)SC
CLD Reference No. 00-0216
Subject: Brandon Bypass Steering Committee Meeting
Location: Brandon
Fire Station
attendees: Bypass Steering
Committee Members and other officials:
Lynn
Saunders Brandon
Selectboard BBSC PBSC
Richard Baker Brandon Citizen BBSC
Peg Flory Pittsford Selectboard BBSC PBSC
Dolores Furnari Brandon Chamber
of Commerce BBSC
Mike Balch Brandon Town Manager BBSC
Dan Peterson VTrans Project
Manager BBSC PBSC
Chris Bean CLD Engineers
Project Manager BBSC PBSC
Greg Riley VTrans, Regional
Planning
Duncan Wilkie VTrans
Archeologist
Chris Borstel Louis Berger
Group Archeologist
Mark Blucher Rutland Regional
Planning Commission
Judith Kmileck Rutland Regional
Planning Commission
Roy Newton Brandon/Pittsford Reporter
Jason Stone CLD Engineers Envir. Specialist
BBSC
- Brandon Bypass
Steering Committee Member
PBSC
– Pittsford Bypass Steering Committee Member
Citizens:
Gordon Halliday Brandon John S. Malewicki, Jr. Brandon
Dan McDonough Brandon Chris Eddy Brandon
Sherry Humiston Brandon Sara Eddy Brandon
Bernard Humiston Brandon Merla Center Brandon
Elaine Mumford Brandon Linda K. Cummings Brandon
Gerry Racette Brandon Phil Sutherland Brandon
David Martin Brandon Ronald D. Eddy, Jr. Brandon
Meeting Notes
1. Introductions
Chris Bean made general
introductions of those present.
2.
VTrans Project Manager
Dan Peterson indicated that there has been no
change in the project manager status.
He is still acting in this capacity and will continue until a
replacement is named.
3. Hill and Hollow Alliance
A group of concerned citizens known as the
"Hill and Hollow Alliance" has formed. The members reside primarily in the area referred to as Sugar
Hollow, along Birch Hill Road, in the Towns of Pittsford and Brandon. A resolution was submitted to the Selectboards
of Pittsford and Brandon. The group
requested an opportunity to summarize their concerns relative to the
Bypasses. The following concerns were
expressed:
·
David Martin:
The group is concerned that westerly bypass alternatives will not be
fully considered. The group recognizes
that US Route 7 has problems and supports the upgrade projects and the study of
"mini-bypasses" around the villages.
The group opposes long bypass alternatives, especially those that would
impact the Sugar Hollow area. A
petition stating the group's concerns and position has been signed by approximately
300 people, and continues to be circulated.
·
Ron Eddy, Jr.:
Does not believe a bypass will solve the problem with US Route 7. Ron Eddy thinks the problem would only be
moved to another location and that environmental impacts associated with a long
bypass are not worth benefits gained.
·
Chris Eddy:
The Sugar Hollow area is valuable black bear habitat, as well as
wintering habitat for deer. Chris Eddy
cited noise, pollution, and accidents (animal-vehicle) as reasons that a bypass
should not be considered in Sugar Hollow.
·
Phil Southerland: The Sugar Hollow area is a valuable resource enjoyed by many for
its scenic beauty and natural resources.
A bypass should not be constructed there. Mini-bypasses are acceptable; a large bypass to the east of US Route
7 would be strongly opposed.
4. Project
Purpose and Need Statement
Prior to the meeting,
the draft Purpose and Need Statement developed for this project was provided to
the Steering Committee for review.
Chris Bean asked those present for comments.
Dan Peterson felt that
in order for the resource agencies to be convinced a bypass is necessary, the
Purpose and Need Statement must describe to some extent how the existing
facility is deficient, and how a bypass would benefit through traffic. As it stands, the Purpose and Need Statement
focuses on local access issues and side street level of service. Others agreed with Dan. Chris explained that quantifying
deficiencies using such standard indicators as highway capacity or level of
service is difficult. The project area
does not lend itself to the standard methods of measuring highway
performance. The absence of signals at
intersections gives through traffic the right of way, resulting in delays for
those accessing US Route 7 from local streets and business and residential
drives. However, the volumes of local
movements are not high enough in any one location to warrant signalization.
Mike Balch suggested there might be other
communities, if not in Vermont then in another state such as Massachusetts,
with current traffic volumes that approach the volumes predicted for the
project area. If an appropriate example
were found, the traffic problems associated with the high volumes may lend
support to the need for a bypass.
Dan Peterson felt that a reasonable approach
might be to assume that with current and anticipated growth in traffic, safety
hazards related to the existing unsignalized intersections would at some point
lead to signalization. Once signals are
installed, the level of service of the main line would be at "F" or
failure. Dan felt it could be argued
that since widening would not be permitted through the villages, this would
help justify bypasses.
Richard Baker requested and it was agreed that
separate Purpose and Need Statements should be developed for Pittsford and
Brandon. He stated that there are too
many intersections and sources of side-friction to signalize. He also noted that any accident that causes
one-way alternating traffic on US Route 7 results in the "failure" of
the main line.
5.
Project
Schedule/Progress Report
Chris Bean updated the
project schedule. Phase I is
essentially complete, though a meeting with the Resource Agencies will be
added, to make the agencies aware of the project and to present the Purpose and
Need Statement for discussion. This
meeting is scheduled for February 7, 2001.
Peg Flory and Lynn Saunders will attend. David Martin indicated that a representative of the Hill and
Hollow Alliance would also attend. The
Phase II schedule has been adjusted.
The next Individual Town Steering
Committee Meetings are targeted for March 8, 2001, at the Otter Valley
Union High School. The Brandon Bypass
Steering Committee Meeting will be from 4:00 - 5:30 PM, and the Pittsford
Bypass Steering Committee Meeting will be from 6:00 - 7:30 PM. A second Resource Agency meeting is slated
for early April, 2001, to discuss conceptual corridors, followed by a third
round of Individual Town Steering Committee Meetings, in early to mid-April. A second Joint Public Informational Meeting
is slated for late April, bringing the project back on schedule.
6. Update on Archeology
VTrans and its
consultant, Louis Berger and Associates (LBA), have created a Predictive Model
for predicting the location of archeologically sensitive areas. To the extent practicable, such areas should
be considered as constraints in the development of conceptual corridors. The Predictive Model developed to date
consists of a compilation of known archeological site information for sites
within the project area, as well as other sites in Vermont. Information such as a site's relationship to
key environmental parameters is used to predict the likelihood of archeological
deposits existing in a given area. For
prehistoric sites, the key parameters are proximity to a water source, the
presence of well-drained soils, and terrain with low to gradual slopes. For historic sites, the key parameter is an
area's proximity to historic roads.
LBA has applied the
Predictive Model to the project area.
Areas of predicted prehistoric and historic archeological resource
sensitivity have been mapped. LBA will
work to provide this information to CLD in ArcView format, for incorporation
into the environmental constraints maps.
7. Environmental
Constraints Maps
Jason Stone presented
the constraints maps developed to date.
The information contained in the maps was provided by the Vermont Center
for Geographic Information and the Rutland Regional Planning Commission. Several maps were shown that group
"like" resources. A portion
of a map depicting all constraints was shown, to demonstrate that there is no
possible way to design a bypass to avoid all resources. Conceptual corridors will be developed to
minimize resource impacts to the extent practicable.
8. Next
Meeting
The next
Individual Town Steering Committee Meetings are targeted for March 8, 2001,
at the Otter Valley Union High School.
The Brandon Bypass Steering Committee Meeting will be from 4:00 - 5:30
PM, and the Pittsford Bypass Steering Committee Meeting will be from 6:00 -
7:30 PM.
CRB:cww
Attachment: Hill and Hollow Alliance Resolution
|
cc: Lynn Saunders |
Brandon |
Mark
Blucher |
RRPC |
|
Peg Flory |
Pittsford |
Mark
Germanowski |
RRPC |
|
Richard Baker |
Brandon |
Susie
Leonard |
RRPC |
|
Jim O’Gorman |
Pittsford |
Judith
Kmileck |
RRPC |
|
Mike Balch |
Brandon |
Kathleen
Ryan |
Landscape
Architect |
|
Hank Pelkey |
Pittsford |
Gary
A. Klinefelter |
VSE |
|
Dan Peterson |
VTrans |
Virginia
Russell |
State
Transportation Board |
|
Alan Neveau |
VTrans |
Jon
Satz |
Store
Owner, Brandon |
|
Scott Newman |
VTrans |
Sen.
Gerry Gossens |
State
Senator |
|
Duncan Wilkie |
VTrans |
Roy
Newton |
Brandon-Pittsford Reporter |
|
Chris Borstel |
Louis
Berger Group |
Ed
Barna |
Rutland Herald |
|
Greg Riley |
VTrans |
Frank
Farnsworth |
Otter Valley Press |
|
Dennis Benjamin |
VTrans |
Harry
McKinlay |
Pittsford |
|
John Narowski |
VTrans |
Lynne
White |
Pittsford |